Negotiated contracts take revisions up to award. Project wage determinations are effective for 180 days. 29 CFR 1.6(c)29 CFR 1.6Code of Federal Regulations, eCFR; Fact Sheet 66D.
What counts as issued
Wage determinations change often; general decisions get weekly modifications, generally on Fridays. The rules below turn on when a revision is issued. For a general wage determination, 29 CFR 1.6(c)(2)(i) says issued “means the date that a revised general wage determination is published on the DOL-approved website”, which is SAM.gov. For a project wage determination it is the date the agency gets actual written notice. A revision includes both a modification and a new annual edition.
Before award
The starting rule is simple: a revision issued before contract award (or before construction starts if there is no award) applies to the project. There are exceptions by contracting method:
| Situation | Latest revision that applies | Rule |
|---|---|---|
| Negotiated contract (for example, a request for proposals) | Revisions issued up to award | 29 CFR 1.6(c)(2)29 CFR 1.6Code of Federal Regulations, eCFR(ii) |
| Sealed bidding | Revisions issued at least 10 days before bid opening, if award comes within 90 days of opening | 29 CFR 1.6(c)(2)29 CFR 1.6Code of Federal Regulations, eCFR(ii)(A), (D) |
| National Housing Act project | Revisions issued before construction starts or the mortgage is initially endorsed, whichever is first | 29 CFR 1.6(c)(2)29 CFR 1.6Code of Federal Regulations, eCFR(ii)(B) |
| Section 8 housing assistance payments project | Revisions issued before construction starts or the agreement to enter into the payments contract is signed, whichever is first | 29 CFR 1.6(c)(2)29 CFR 1.6Code of Federal Regulations, eCFR(ii)(C) |
| No contract award | Revisions issued before construction starts | 29 CFR 1.6(c)(2)29 CFR 1.6Code of Federal Regulations, eCFR(ii) |
The Resource Book puts the agency's job this way: it must make sure the up-to-date wage determination is in the bid documents and that modifications are included up to award or other lock-in date. In practice, an amendment to the solicitation brings in the new modification.
Sealed bids: the 10-day and 90-day rules
Under 29 CFR 1.6(c)(2)29 CFR 1.6Code of Federal Regulations, eCFR(ii)(A), “a revised wage determination issued at least 10 calendar days before the opening of bids is effective with respect to the solicitation and contract”. A revision issued less than 10 days before opening also applies, unless the agency finds there is not reasonable time to notify bidders and puts a report of that finding in the contract file. A revision issued after bid opening needs no report and does not apply, as long as award comes within 90 days of opening. Fact Sheet 66D: “This wage determination will apply to the contract even if a more recent wage determination is issued prior to contract award, as long as the contract is awarded within 90 days of the bid opening date.”
If award has not happened within 90 days of bid opening, any revision issued before award applies, unless the agency head (or designee) asks for and gets an extension of the 90-day period from WHD. The request needs a written finding that the extension is necessary and proper in the public interest to prevent injustice or undue hardship or to avoid serious impairment of government business.
| Example timeline (sealed bid) | Result |
|---|---|
| Modification 4 published 14 days before bid opening | Modification 4 is in the solicitation and contract |
| Modification 5 published 6 days before bid opening | Modification 5 applies unless the agency documents that there was not reasonable time to notify bidders |
| Modification 6 published 20 days after bid opening; award 45 days after opening | Modification 6 does not apply |
| Award slips to 120 days after opening, no extension | Any modification issued before award applies |
For bidders, the practical step is to check SAM.gov before pricing. SAM.gov publishes a list of DBAs to be revised in the next publication cycle, which warns of a coming modification. The Resource Book says “contractors should be advised/encouraged to review the Davis-Bacon wage determinations in the bid documents” and raise questions during the advertising period, when out-of-date rates and errors can still be fixed.
Project wage determinations
A project wage determination, requested by an agency on Form SF-308 when no general decision fits, works differently. It “will be effective for 180 calendar days from the date of such determinations”; if it is not in a contract (or construction has not started) within that time, it is void (29 CFR 1.6(a)(3))29 CFR 1.6Code of Federal Regulations, eCFR. If it may expire between bid opening and award, the agency should request a new one in time. If it expires after bid opening for unavoidable reasons, the agency may ask WHD to extend it, with the same kind of written finding.
After award
The Resource Book states the default: modifications and reissued wage determinations “issued after award of a contract generally do not apply to a contract”. A wage determination properly in your contract sets the minimum rates for its whole term. There are three exceptions in 29 CFR 1.6(c)(2)29 CFR 1.6Code of Federal Regulations, eCFR(iii).
Substantial added work, added time, or options. When a contract or order is changed to add substantial construction, alteration or repair not within the original scope, or to require work for an additional period not originally obligated, including the exercise of an option to extend the term, the agency must include the most recent revision at the time of the change. “This does not apply where the contractor is simply given additional time to complete its original commitment or where the additional construction, alteration, and/or repair work in the modification is merely incidental.”
What counts as a substantial change in scope (AAM 249)
WHD's All Agency Memorandum 249 (dated January 17, 2025, and posted on the All Agency Memoranda list on SAM.gov on February 4, 2025) explains this exception. Its starting point: “substantial changes to the scope of work for a prime contract are treated as a new contract for the purpose of determining the applicable wage determination(s) for the remainder of the project”. WHD sets no single dollar test, because projects differ so much in size. Its example: “while an additional $20,000 of work involving 200 labor-hours might be only a minor addition to a multi-million-dollar construction project, it would be a significant addition to a $75,000 contract for repairs”. AAM 249 then lists changes that generally require an update:
| Added work | Generally substantial? (AAM 249) |
|---|---|
| Work on a separate building or work not in the original scope (for example, a second building added to a renovation contract) | Yes, unless the work on the separate building is minimal |
| A type of construction with no wage determination in the contract | Yes, if it would have required its own wage determination at award (the multiple wage determination threshold; see construction types) |
| Work in a different locality (for example, a second county added to a highway repair contract) | Yes |
| Work added as part of, or with, a novation to a new contractor | Generally yes |
| Any other added work that costs more than the multiple wage determination threshold | Generally yes |
When AAM 249 was issued, it put that threshold at “currently either 20% of total project costs or $2.5 million”. AAM 251 (August 15, 2025) later raised the dollar figure for multiple wage determinations to $3.3 million; AAM 249 has not been reissued, so ask the contracting officer which figure the agency is applying.
AAM 249 also answers questions agencies kept asking:
- It is not the same as a cardinal change. A change can stay within the contract's changes clause and still be substantial added work, so “agencies cannot solely rely on a determination that a change is not a cardinal change”.
- The update looks forward only. “In no circumstances will the updated wage determination(s) apply retroactively to the work performed prior to the modification.” In most cases it covers all work left on the contract, old scope and new; it may be limited to the added work when that work is clearly distinct (another locality, a separate building that does not affect the rest, or a new construction type).
- Options count whether exercised by one party or both: the rule applies “for both unilateral and bilateral exercises of options”. But “an updated wage determination is not required where the contractor is simply given additional time to complete its original commitment”.
- For task orders under an umbrella contract, once an order carries the updated wage determination, “future updates to the wage determination(s) in the underlying contract do not affect that order”.
Open-ended contracts. For contracts with construction over a period not tied to one project, such as IDIQ repair contracts, long-term operations and maintenance contracts, and schedule contracts or blanket purchase agreements, the agency must add the most recent revisions on each anniversary of award (or of construction start if no award), unless DOL approved another process in writing. The updated wage determination applies to work that begins or is obligated in the next 12 months, until that work is done. Task orders must carry the updated wage determination, and once incorporated it stays for the life of the order unless the order adds substantial work or exercises options.
Both. A contract that is open-ended and has options gets updates at both points, and the date of a qualifying change or option becomes the new anniversary date.
Clean energy credit projects follow a different timing rule set by Treasury: generally the general wage determination in effect when the contract is signed. See supplemental wage determinations for clean energy projects.
When the wrong wage determination was used
Most of the time, the modification in your contract is the one you pay. These are the cases where it can change:
| Situation | What happens | Rule |
|---|---|---|
| Clerical error in the wage determination | WHD may correct it at any time; the correction goes into ongoing contracts, retroactive to the start of construction | 29 CFR 1.6(d)29 CFR 1.6Code of Federal Regulations, eCFR |
| WHD gives written notice before award that the wrong wage determination or schedule was used, or one was withdrawn after an ARB decision | That wage determination may not be used | 29 CFR 1.6(e)29 CFR 1.6Code of Federal Regulations, eCFR |
| Contract awarded without the correct wage determination | The agency must terminate and resolicit, or add the correct one by change order or similar, generally retroactive to award; within 30 days of a WHD request | 29 CFR 1.6(f)29 CFR 1.6Code of Federal Regulations, eCFR |
| Federal funding approved after award | The wage determination in effect at award or construction start is added retroactively, unless WHD allows the funding approval date | 29 CFR 1.6(g)29 CFR 1.6Code of Federal Regulations, eCFR |
When a missing wage determination is added after award, the regulation protects the contractor: “The contractor must be compensated for any increases in wages resulting from incorporation of a missing wage determination.” Workers are owed the higher rates back to the effective date.
29 CFR 1.6(f)(4)29 CFR 1.6Code of Federal Regulations, eCFR, as saved before the court ruling, also says the correct wage determination is effective by operation of law under 29 CFR 5.5(e)29 CFR 5.5Code of Federal Regulations, eCFR. A federal court vacated all of 5.5(e) on June 24, 2026 (AGC v. DOL, No. 5:23-cv-272-H (N.D. Tex.), Final Judgment, Doc. 108). The judgment does not name 1.6(f)(4), but the 5.5(e) provision that sentence relies on was vacated, so do not count on incorporation by operation of law. The retroactive incorporation steps in 1.6(f)(1) to (3) are not affected. See the 2023 rule in 2026.
Subcontracts and certified payroll
The prime contract's wage determinations flow down. Fact Sheet 66D: “Wage determinations incorporated into a prime contract must be incorporated into all subcontracts.” A subcontractor signed months after award still uses the prime contract's modification, not the one on SAM.gov that day. On each certified payroll, the WH-347 instructions say to “Enter the wage determination number(s) and revision number(s) included in the covered contract”, listing every one that applied to the work that week. See the WH-347 guide and common certified payroll mistakes.
Questions filers ask
A new modification came out after we signed. Do we have to pay the new rates?
Generally no. Revisions issued after award do not apply unless the contract is changed to add substantial work or time, an option is exercised, or it is an open-ended contract updated on its anniversary.
Does a no-cost time extension bring in a new wage determination?
No. 29 CFR 1.6(c)(2)29 CFR 1.6Code of Federal Regulations, eCFR(iii)(A) says the update does not apply where the contractor is simply given more time to finish its original commitment.
We bid on a sealed bid and award took four months. Which modification applies?
If award came more than 90 days after bid opening and the agency did not get an extension from WHD, any revision issued before award applies, and the agency should add it to the contract.
Our subcontract was signed a year after the prime contract. Which rates do we use?
The wage determinations in the prime contract, as Fact Sheet 66D says they must be incorporated into all subcontracts. If the prime contract was later changed in a way that required an update, use the updated one.
Do options always trigger a new wage determination?
Exercising an option to extend the term does, under 29 CFR 1.6(c)(2)29 CFR 1.6Code of Federal Regulations, eCFR(iii)(A): the agency must include the most recent revision at the time the option is exercised.
Does a change order bring in the newest wage determination?
Only if it adds substantial work outside the original scope. AAM 249 says a separate building, a new locality, a new construction type or added work above the multiple wage determination threshold generally counts. The update applies from the date of the change, never to work already done.