Send requests to IRAprevailingwage@dol.gov. 26 CFR 1.45-7(b)(3)26 CFR 1.45-7Code of Federal Regulations, eCFR; DOL WHD, Prevailing Wage and the Inflation Reduction Act.
Start with the general wage determination
The Treasury regulation for the production credit, 26 CFR 1.45-7(b), sets the wage determination rules, and the investment credit rule applies them too: 26 CFR 1.48-1326 CFR 1.48-13Code of Federal Regulations, eCFR refers to “satisfying the prevailing wage requirements under § 1.45-7(a)(2) and (3) and (b) through (d)”. The default is a general wage determination from SAM.gov, the same ones used on Davis-Bacon contracts. Under 1.45-7(b)(2)(i), “The applicable general wage determination is the general wage determination in effect for the specified type of construction in the geographic area at the time a contract for the construction, alteration, or repair of the facility is executed” by the taxpayer and a contractor. It carries through to that contractor's subcontracts. With no contract, or if the contract date cannot reasonably be determined, use the one in effect when work starts.
For utility-scale solar and wind, DOL's IRA page says to use the heavy construction wage determination for the area. If the facility spans more than one area, the wage determination for each area applies to the work there; DOL's page adds that paying the highest rate for each classification across those wage determinations also satisfies the rule. Look up wage determinations at SAM.gov wage determinations, and see the four construction types and how to read a wage determination.
When a supplemental wage determination is available
DOL's IRA page stresses that this is the exception: “In very limited circumstances, a general wage determination may not have been published” for the area or type of construction. Under 26 CFR 1.45-7(b)(3)(i)26 CFR 1.45-7Code of Federal Regulations, eCFR, a request is available in three situations:
| Situation | What to ask DOL for |
|---|---|
| No general wage determination for the area and type of construction | A supplemental wage determination |
| A general wage determination exists but a needed classification is not listed | An additional classification and wage rate |
| The facility's work spans more than one contiguous geographic area | Optionally, a supplemental wage determination for the facility |
On the third case the regulation says: “A taxpayer, contractor, or subcontractor may also request a supplemental wage determination if the location of the facility involves work by covered laborers and mechanics that spans more than one contiguous geographic area.” Do not ask for a supplemental wage determination just because you dislike the general rates. DOL says that on receiving a request, “the Wage and Hour Division will determine whether an applicable general wage determination exists (in which case the request will be denied)”.
Supplemental, additional classification or conformance
| Supplemental wage determination | Additional classification (credit project) | Davis-Bacon conformance | |
|---|---|---|---|
| Used when | No general WD fits | A class is missing from the general WD | A class is missing on a Davis-Bacon contract |
| Who asks | Taxpayer, contractor or subcontractor | Taxpayer, contractor or subcontractor | The contracting officer, on SF-1444 |
| Sent to | IRAprevailingwage@dol.gov | IRAprevailingwage@dol.gov | DBAconformance@dol.gov |
| Timing | No more than 90 days before contract execution | Any time after contract execution | When the need arises |
| Rule | 26 CFR 1.45-7(b)(3)26 CFR 1.45-7Code of Federal Regulations, eCFR | 26 CFR 1.45-7(b)(3)26 CFR 1.45-7Code of Federal Regulations, eCFR | 29 CFR 5.5(a)(1)29 CFR 5.5Code of Federal Regulations, eCFR(iii) |
For an additional classification, DOL's IRA page says WHD applies the same three tests as a Davis-Bacon conformance: the wage determination lacks the classification, the classification is used in the area, and the proposed rate bears a reasonable relationship to rates in the same category. If only the first two are met, WHD approves the classification and sets the rate itself. See conformance for how the reasonable relationship test works.
When to ask
Under 26 CFR 1.45-7(b)(3)26 CFR 1.45-7Code of Federal Regulations, eCFR(ii)(B), a supplemental wage determination request should be made “no more than 90 days before the taxpayer (or the taxpayer's designee, assignee, or agent) expects to execute the contract” for the work. With no contract, the 90 days run from the start of construction, alteration or repair.
An additional classification request can be made any time after the contract is signed. With no contract, it should be no more than 90 days before work starts. If the need could not reasonably be seen in advance, ask as soon as practicable after you find it (1.45-7(b)(3)(ii)(C))Treas. Reg. 1.45-7Treasury regulations, eCFR.
DOL's IRA page still describes the 90 days as running from the start of construction. The page carries its own banner: “Some of the information on this webpage may be out of date but will be updated soon.” The Treasury regulation, which measures from contract execution, is the rule for the credit, and the IRS FAQs say the same.
What the request must include
Email IRAprevailingwage@dol.gov (or write to the WHD Branch of Construction Wage Determinations). Under 26 CFR 1.45-7(b)(3)26 CFR 1.45-7Code of Federal Regulations, eCFR(ii)(D) the request must include:
- The name of the taxpayer, contractor or subcontractor making the request.
- Any general wage determination that applies to the work.
- A description of the work, the types of construction involved and, for a mixed project, the expected cost breakdown by type.
- The geographic area, with the facility's name and address if known.
- The date the contract is expected to be signed (supplemental WD) or was signed (additional classification).
- The start date of construction, alteration or repair.
- Each labor classification needed that is not on an applicable general wage determination, with the duties each will perform.
- The proposed wage rate and any bona fide fringe benefits for each classification.
- Any pertinent wage payment information, anything else DOL's forms and instructions require, and anything else you want DOL to consider.
After DOL answers
WHD tells the requester which wage determination, classifications and rates to use. Two clocks run under 26 CFR 1.45-7(b)(3)26 CFR 1.45-7Code of Federal Regulations, eCFR(iii):
Supplemental wage determinations. “Supplemental wage determinations issued by the Wage and Hour Division are effective for 180 calendar days from the date such determinations are issued.” If it is not in the contract (or construction has not started) within that time, it lapses and you must request a new one.
Additional classifications. WHD resolves them “within 30 days of receipt of the request or will advise the requester within the 30-day period that additional time is necessary”.
Once you have the rates, they work like any other wage determination: pay at least the rate and fringe for the classification of work done, flow them down to subcontractors, and update them if the contract is later changed to add substantial work or time, or an option is exercised (1.45-7(b)(5))Treas. Reg. 1.45-7Treasury regulations, eCFR. Keep the request, DOL's reply and the wage determination in the credit file. DOL's IRA page lists records that may show compliance, starting with “documentation identifying the applicable wage determination”, then the workers, their classifications, their hours in each, and the rates paid.
If you disagree with a general wage determination or with DOL's answer, 26 CFR 1.45-7(b)(4)26 CFR 1.45-7Code of Federal Regulations, eCFR points to reconsideration by the WHD Administrator under 29 CFR 1.829 CFR 1.8Code of Federal Regulations, eCFR and 5.13, and appeal to the Administrative Review Board under 29 CFR part 729 CFR part 7Code of Federal Regulations, eCFR.
Offshore facilities
For a facility in an offshore area within the outer continental shelf, when no general wage determination is available, you need not request a supplemental one. Under 26 CFR 1.45-7(b)(3)26 CFR 1.45-7Code of Federal Regulations, eCFR(iv), the taxpayer, contractor or subcontractor may rely on the general wage determination for the relevant type of construction in the geographic area closest to the facility.
Other laws still apply
Meeting the credit's wage rules does not displace state prevailing wage laws or other wage and hour laws on the same job. DOL's IRA page says such laws “impose separate legal requirements from the Inflation Reduction Act and must be complied with where applicable”. If the project is also publicly funded, check which prevailing wage rules apply and your state's page under state prevailing wage laws. For the credit rules themselves, see clean energy credits.
Questions filers ask
Do I need a supplemental wage determination for a solar farm?
Usually not. DOL says to use the heavy construction general wage determination for the area, and supplemental wage determinations are for the very limited cases where no general one exists. A request where a general one exists will be denied.
Which wage determination modification applies to a credit project?
Under 26 CFR 1.45-7(b)(2)26 CFR 1.45-7Code of Federal Regulations, eCFR, the general wage determination in effect when the taxpayer and contractor sign the contract. Without a contract, the one in effect when work starts.
How early can I request a supplemental wage determination?
No more than 90 days before you expect to sign the construction contract (or, with no contract, before work starts). It is effective for 180 days from issue.
Where do I send the request?
By email to IRAprevailingwage@dol.gov, or to the WHD Branch of Construction Wage Determinations in Washington, DC, under 26 CFR 1.45-7(b)(3)26 CFR 1.45-7Code of Federal Regulations, eCFR(ii)(A).
Can my contractor ask instead of me?
Yes. The regulation lets the taxpayer, a contractor or a subcontractor make the request. The taxpayer remains responsible for the wages on the credit.