Which wage determination modification applies? Lock-in date calculator

A wage determination modification published before contract award generally applies, with exceptions. On sealed bids, one published at least 10 calendar days before bid opening is in, and one published after opening stays out if award comes within 90 days. Enter your dates to see whether a modification is in your contract, and the rule that decides it.

Updated November 21, 2026Sources 29 CFR 1.6(a), (c), (d), (e), (f) and (g); Fact Sheet 66D; DOL Prevailing Wage Resource Book (Davis-Bacon Wage Determinations)Privacy runs in your browser; nothing you enter is sent or stored
The rule differs by contracting method.
Most contracts use a general decision.
From the modification record in the decision.
Sealed bids only.
Leave blank if not awarded yet.
HUD-assisted housing.
Needed with no award and on housing projects.
Checks the 180-day life.
The date the contract was changed.
29 CFR 1.6(d)29 CFR 1.6Code of Federal Regulations, eCFR, (e), (f) and (g).

How the calculator decides

Once a wage determination is in your contract, “the wage determination generally applies for the duration of the contract or project, except as specified in this section” (29 CFR 1.6(a)(1)). The calculator finds the lock-in date under 29 CFR 1.6(c), checks what happened after award, and quotes the rule that decides. The which modification applies guide covers the rules in depth.

The date that counts is the date issued, which “means the date that a revised general wage determination is published on the DOL-approved website or the date that the contracting agency receives actual written notice of a revised project wage determination” (29 CFR 1.6(c)(2)(i))29 CFR 1.6Code of Federal Regulations, eCFR. For a general decision, use the date in its own modification record on SAM.gov wage determinations (the decoder explains the header), and confirm it with the contracting officer if it decides your bid.

Sealed bids: the 10-day and 90-day rules

Under 29 CFR 1.6(c)(2)29 CFR 1.6Code of Federal Regulations, eCFR(ii)(A), “a revised wage determination issued at least 10 calendar days before the opening of bids is effective with respect to the solicitation and contract”. A revision issued less than 10 days before opening also applies unless the agency finds there was not reasonable time to notify bidders and puts a report in the contract file. A revision published after opening stays out if award comes within 90 days; if not, revisions up to award apply unless WHD extends the 90 days (1.6(c)(2)(ii)(D)). These examples were run through the calculator:

DatesResultWhy
Bid opens Mar 17, 2026 (Tue); published Mar 7, 2026 (Sat)InExactly 10 calendar days; the weekend counts
Same bid; published Mar 9, 2026In, unless the agency makes a finding8 days, under 10
Bid opens Mar 5, 2026; published Feb 23, 2026In10 days across the end of February
Bid opens Jan 5, 2027; published Dec 27, 2026In, unless the agency makes a finding9 days across the new year
Bid opens Jan 15, 2026; award Apr 15, 2026; published Feb 6, 2026OutAward on day 90 is within 90 days
Same, but award Apr 16, 2026InDay 91, no extension

Negotiated contracts, no award, and housing projects

Without sealed bidding there is no 10-day window: “If a revised wage determination is issued before contract award (or the start of construction when there is no award), it is effective with respect to the project” (29 CFR 1.6(c)(2)(ii))29 CFR 1.6Code of Federal Regulations, eCFR. HUD-assisted housing locks in at the start of construction or, if earlier, the initial mortgage endorsement (National Housing Act) or the signing of the agreement to enter into the payments contract (Section 8), with a 90-day limit like the bid rule (1.6(c)(2)(ii)(B) to (D)).

After award: changes, options and open-ended contracts

After award, a new modification generally does not apply. The exceptions in 29 CFR 1.6(c)(2)29 CFR 1.6Code of Federal Regulations, eCFR(iii):

EventWhat comes inRule
Change adding substantial work outside the scope or an added period, or an option to extend the termThe most recent revision on the date of the change or option1.6(c)(2)(iii)(A)
More time to finish the original work, or merely incidental added workNothing new1.6(c)(2)(iii)(A)
Open-ended contract (IDIQ repairs, long-term operations and maintenance, schedule contracts, BPAs)The most recent revision on each anniversary of award; a change or option resets the anniversary1.6(c)(2)(iii)(B), (C)

What counts as substantial is explained in WHD’s All Agency Memorandum 249, issued by WHD Administrator Jessica Looman (dated January 17, 2025; posted on the SAM.gov memo list February 4, 2025). Its starting point: “substantial changes to the scope of work for a prime contract are treated as a new contract for the purpose of determining the applicable wage determination(s) for the remainder of the project”. The calculator takes your answer on that point as given.

Corrections, the wrong wage determination and late funding

WHD may correct a clerical error at any time, retroactive to the start of construction (29 CFR 1.6(d))29 CFR 1.6Code of Federal Regulations, eCFR. If the wrong wage determination was used, WHD can bar it before award (1.6(e)); after award the agency must add the correct one, retroactive to award, and “The contractor must be compensated for any increases in wages resulting from incorporation of a missing wage determination.” (1.6(f)). If Related Act funding is approved after award, the rates in effect on the award date apply, retroactively (1.6(g)).

The tool does not rely on incorporation by operation of law under 29 CFR 5.5(e)29 CFR 5.5Code of Federal Regulations, eCFR, which 1.6(f)(4) cites: a federal court vacated all of 5.5(e) on June 24, 2026 (AGC v. DOL, No. 5:23-cv-272-H (N.D. Tex.), Final Judgment, Doc. 108, June 24, 2026). A wrong or missing wage determination is fixed only when the agency incorporates the correct one. See the 2023 rule in 2026.

How days are counted

The 10-day rule says calendar days, so weekends and holidays count and a date on a Saturday does not move. The 90-day rules do not say business days either, so the calculator counts calendar days and flags a weekend date without moving it. Month ends, leap years and the new year need no special handling. An award on February 29 gets its anniversary on February 28 in other years; the rule does not address that, so confirm it with the agency. Clean energy credit projects follow Treasury’s timing rule; see wage determinations for clean energy projects.

General information, not legal advice. The contracting agency decides which wage determination goes in the contract, and questions go to WHD under 29 CFR 1.6(b)(3)29 CFR 1.6Code of Federal Regulations, eCFR.

Questions filers ask

A modification came out after we signed. Do we pay the new rates?

Generally no, unless the contract is changed to add substantial work or time, an option is exercised, or it is an open-ended contract updated on its anniversary.

Do weekends count in the 10-day rule?

Yes. The rule says at least 10 calendar days before the opening of bids, so every day counts and a weekend date does not move.

Award took four months after bid opening. Which modification applies?

If award came more than 90 days after opening and the agency got no extension from WHD, any revision issued before award applies.

Does a no-cost time extension bring in a new wage determination?

No. The rule excludes a change that simply gives the contractor more time to complete its original commitment.