No state law
Law
Repealed 2015; local mandates barred
Threshold
None
Agency
None
Certified payroll
None
State prevailing wage laws

Indiana prevailing wage law

Indiana repealed its common construction wage statute, IC 5-16-7, in 2015 (P.L.252-2015). The old law still governs public works contracts awarded before July 1, 2015, and for later contracts IC 5-16-7.2-5 bars public agencies from setting a wage scale unless federal or state law provides otherwise. Federal Davis-Bacon rates apply to federal and federally assisted work, and state highway bids carry their own hourly rate rule.

Updated November 21, 2026Sources IC 5-16-7, 5-16-7.1 and 5-16-7.2 (P.L.252-2015); IC 8-23-9-22; 40 U.S.C. 3142; 23 U.S.C. 113; IRS prevailing wage rules

Status of the state law

The 2025 Indiana Code shows IC 5-16-7 as “Repealed by P.L.252-2015, SEC.9.” That chapter was the common construction wage statute, the Indiana version of a prevailing wage law.

The repeal was not retroactive. IC 5-16-7.1-2 says the old statute “applies to a public works contract awarded before July 1, 2015, and shall be enforced as if the common construction wage statute had not been repealed”. So a claim on a contract awarded before that date is judged under the old law; anything awarded later is not.

Limits on state agency and local wage rules

For public works contracts awarded after June 30, 2015, IC 5-16-7.2-5 says: “Unless federal or state law provides otherwise, a public agency may not: (1) establish; (2) mandate; or (3) otherwise require; a wage scale or wage schedule for a public works contract awarded by the public agency.” Public agency has the meaning set out in IC 5-30-1-11.

There is one carve out. Under IC 5-16-7.2-1(b), the chapter “does not apply to contracts awarded by the Indiana department of transportation when IC 8-23-9 applies”. That chapter has its own wage rule for state highway bids, below. See local prevailing wage bans for other states.

What still applies on a Indiana project

No state rate does not mean no rates. The federal Davis-Bacon Act covers “every contract in excess of $2,000, to which the Federal Government or the District of Columbia is a party, for construction, alteration, or repair” of public buildings and public works, and a federal job in Indiana is no exception. See Davis-Bacon coverage.

Federal money on a state or local job brings its own rules through the Related Acts. Federal-aid highway work is the common case: workers “shall be paid wages at rates not less than those prevailing on the same type of work on similar construction in the immediate locality”, as the Secretary of Labor determines. On those jobs the wage determination is in the contract and the weekly certified payroll rules apply.

Clean energy projects are a third path. A taxpayer that wants the increased credit must “Pay laborers and mechanics employed in construction, alteration or repair no less than applicable prevailing wage rates”, and “The U.S. Department of Labor determines the applicable prevailing wage requirements for each class of laborers and mechanics”. That holds in Indiana as in every state; see the clean energy section.

Kind of workWage ruleRates come from
Federal contract over $2,000Davis-Bacon Act (40 U.S.C. 3142)40 U.S.C. 3142United States Code, Cornell LIIDOL wage determination in the contract
State or local job with federal moneyThe Related Act in the funding law, e.g. 23 U.S.C. 11323 U.S.C. 113United States Code, Cornell LII for federal-aid highwaysDOL wage determination in the contract
Clean energy project claiming the increased creditIRS prevailing wage and apprenticeship rulesDOL determination for the area and type of work
State or local job with only state or local moneyNo state wage scale for contracts awarded after June 30, 2015 (IC 5-16-7.2-5)None set by the state

The state highway bid rule

IC 8-23-9-22 still applies to state highway work: “A bid submitted for the construction or betterment of a state highway must contain a statement stipulating the hourly rate for laborers.” “The hourly rate may not be lower than the hourly rate paid for common labor by the department.” The rate in the bid becomes part of the contract. This is a floor tied to INDOT's own common labor rate, not a full prevailing wage schedule; on federal-aid highway jobs the federal determination applies as well.

Questions filers ask

When did Indiana repeal its prevailing wage law?

P.L.252-2015 repealed IC 5-16-7. It still applies to public works contracts awarded before July 1, 2015; IC 5-16-7.2 governs contracts awarded after June 30, 2015.

Can an Indiana city set a wage scale for its project?

IC 5-16-7.2-5 bars a public agency from establishing, mandating or otherwise requiring a wage scale for its public works contract unless federal or state law provides otherwise.

Do INDOT contracts have a wage requirement?

State highway bids must state an hourly rate for laborers no lower than INDOT's common labor rate (IC 8-23-9-22). Federal-aid projects also carry the DOL wage determination under 23 U.S.C. 11323 U.S.C. 113United States Code, Cornell LII.

Where do I read a federal wage determination for an Indiana job?

It is in the contract documents. See how to read a wage determination.