Base 20 cents per gallon, $1.00 with PWA, before inflation and times the emissions factor. No credit for fuel sold after December 31, 2029. Form 7218 plus Form 7220. IRC 45Z(f)(6)IRC 45ZInternal Revenue Code, Cornell LII; Form 7218 instructions.
What the credit is
Section 45Z, the clean fuel production credit, applies to transportation fuel produced after December 31, 2024. It pays per gallon (or gallon equivalent) of transportation fuel that a taxpayer produces at a qualified facility and sells to an unrelated person for blending, for use in a trade or business, or at retail. The fuel must have an emissions rate of not more than 50 kilograms of CO2e per mmBTU, the producer must be registered under section 4101, and the amount is scaled by an emissions factor: the lower the fuel's emissions rate, the higher the factor. A facility claiming 45V or 45Q is not a qualified facility for 45Z. The credit uses the prevailing wage and apprenticeship (PWA) rules for its higher amount.
Base amount vs increased amount
The statute sets two amounts. For fuel from a facility that does not meet PWA, “the applicable amount shall be 20 cents”. For a facility that meets both the wage and apprenticeship paragraphs, “the applicable amount shall be $1.00”. Both are adjusted for inflation and multiplied by the emissions factor.
| Fuel | Base (no PWA) | With PWA | Source |
|---|---|---|---|
| Non-SAF fuel sold in 2025 | 21 cents | $1.06 | Form 7218 instructions (factor 1.0611) |
| Sustainable aviation fuel sold in 2025 | 37 cents | $1.86 | Form 7218 instructions |
| All fuel produced after 2025 | 20 cents before inflation | $1.00 before inflation | 45Z(a)(2); P.L. 119-21 sec. 70521(g) |
The Form 7218 instructions put the 2026 change this way: “For all fuel produced after 2025 the applicable amount before adjusting for inflation is either $0.20 (if PWA requirements are not met) or $1.00 (if PWA requirements are met)”. The special higher rate for sustainable aviation fuel ended for fuel produced after 2025. The 2026 inflation adjusted figures were not in the sources we read. Unlike the electricity credits, 45Z has no 1 MW exception and no exception for construction that began before January 29, 2023: the statute reaches the $1.00 amount only through PWA.
2026 status after P.L. 119-21
Section 70521 of P.L. 119-21 extended and narrowed the credit:
| Change | Rule | Effective |
|---|---|---|
| End date | “This section shall not apply to transportation fuel sold after December 31, 2029” (was 2027) | Enacted July 4, 2025 |
| Feedstock | Fuel must be derived only from feedstock produced or grown in the United States, Mexico or Canada | Fuel produced after December 31, 2025 |
| SAF rate | Separate higher SAF amounts removed | Fuel produced after December 31, 2025 |
| Specified foreign entity | No credit | Tax years beginning after July 4, 2025 |
| Foreign-influenced entity | No credit | Tax years beginning two years after July 4, 2025 |
So as of November 2026 the credit is open, and the PWA increase is worth the same fivefold multiple it was in 2025. Because 45Z is a production credit on sales through 2029, the wage obligation on repairs runs every year you claim it. See which credits carry the wage rules in 2026.
Which PWA rules apply
45Z(f)(6) and (7) borrow the 45 rules: rules similar to 45(b)(7) for wages, and “Rules similar to the rules of section 45(b)(8) shall apply” for apprenticeship. For a facility placed in service after 2024, the Form 7220 instructions say “Prevailing wage requirements apply to any construction, alteration, or repair of a facility placed in service after 2024”.
| Rule | Facility placed in service after 2024 | Facility placed in service before 2025 |
|---|---|---|
| Prevailing wage, construction | Yes | No |
| Prevailing wage, alteration or repair | Yes | Yes, in tax years beginning after 2024 for which the credit is allowed |
| Apprenticeship | Construction only | Transition rule (see below) |
| Cure for wage failures | 45(b)(7)(B) | 45(b)(7)(B) |
| 1 MW or pre-2023 construction exception | None | None |
Biofuel and renewable diesel plants run on turnarounds. A turnaround that replaces a reactor internal or rebuilds a pump is repair work, and crews on it must be paid the prevailing rate for the year's gallons to carry the $1.00 amount. Routine maintenance, such as inspections, cleaning, filter changes and calibration, is not covered. Plan the classification for each turnaround contractor before the shutdown starts, and require weekly payrolls (see PWA records). A short turnaround can bring in dozens of contractor workers for a few weeks, and each underpaid worker is a separate $5,000 penalty for the year, so check the first weekly payroll from each contractor before the second week is paid. If a trade has no classification on the wage determination, ask DOL for one before the work starts (see supplemental wage determinations for IRA projects).
Plants placed in service before 2025
Many 45Z claimants run ethanol, biodiesel or renewable diesel plants built years ago. 45Z(f)(6)(B) says that for those facilities the construction rule does not apply, and the repair rule is read as applying “with respect to any taxable year beginning after December 31, 2024, for which the credit is allowed under this section”. The Form 7218 instructions put it plainly: for those facilities the taxpayer “is subject to the prevailing wage requirements for the alteration or repair of the facility with respect to any tax year beginning after 2024, for which the section 45Z credit is allowed”.
On apprenticeship, the Form 7218 instructions add a transition rule: “The taxpayer isn't subject to the apprenticeship requirements with respect to construction of a facility that occurs on or before 90 days after June 25, 2024”. In practice, an older plant claiming the $1.00 amount must pay prevailing wages to every contractor crew doing alteration or repair work in each credit year, and report it on Form 7220. If a turnaround contractor underpaid, the cure is back pay plus interest and $5,000 per worker (see correction and penalties).
What to file
- Claim the credit on Form 7218, Clean Fuel Production Credit, answering the PWA question on line 7 and using the increased amount in Part III, column (g).
- The instructions then require Form 7220: “File a separate Form 7220 for each qualified facility for which you are claiming increased credit amounts”.
- Each year you claim the increased amount, report that year's alteration and repair work on Form 7220 (or attach the signed no-alterations statement).
- Report any PWA penalties on Form 4255.
- Keep payroll, classification and apprentice records under Treas. Reg. 1.45-12Treas. Reg. 1.45-12Treasury regulations, eCFR.
The statute is at 26 U.S.C. 45Z; the PWA filing rules are on the Form 7220 page and the apprentice share is explained on the apprenticeship requirement page.
Questions filers ask
Does 45Z require prevailing wages?
Only for the higher amount. Without PWA the base is 20 cents a gallon (before inflation and the emissions factor); with PWA it is $1.00.
Our ethanol plant was built in 2015. Do we owe prevailing wages?
Not for the original construction. To claim the $1.00 amount, crews on alterations or repairs in tax years beginning after 2024 for which you claim the credit must be paid prevailing wages.
Is there a small plant exception?
No. 45Z has no 1 MW exception and no exception for construction that began before January 29, 2023.
When does 45Z end?
The credit does not apply to fuel sold after December 31, 2029, after the 2025 law extended it from 2027.
Is routine plant maintenance covered?
No. Prevailing wage applies to construction, alteration and repair. Inspections, cleaning, filter changes and calibration after the plant is in service are routine maintenance.