Clean energy credits: IRS wage and apprentice rules

Section 45Y and 48E: wage and apprentice rules

Section 45Y pays a credit per kilowatt hour and 48E a percentage of the investment for zero-emission electricity and storage. Meeting the prevailing wage and apprenticeship rules raises 45Y from 0.6 to 3.1 cents per kWh in 2026 and 48E from 6% to 30%. After the 2025 budget law, wind and solar must have begun construction by July 4, 2026 or be in service by the end of 2027; other technologies stay open. This is general information, not tax advice.

Updated November 21, 2026Sources IRC 45Y and 48E (as amended by P.L. 119-21, secs. 70512 and 70513); IRC 48(a)(10); Treas. Reg. 1.45-7, 1.45-8 and 1.48-13; Notice 2025-42; Instructions for Form 7220

What the credits are

Section 45Y (clean electricity production credit) and section 48E (clean electricity investment credit) apply to electricity facilities and energy storage placed in service after December 31, 2024. They are technology neutral: a facility qualifies if its greenhouse gas emissions rate is not greater than zero, whatever the source. A taxpayer claims one or the other for a facility, not both. 45Y pays for 10 years, per kWh sold to an unrelated person; a facility is a qualified facility only “during the 10-year period beginning on the date the facility was originally placed in service”. 48E is a one-time credit equal to a percentage of the qualified investment in the facility or in energy storage technology. Both use the same prevailing wage and apprenticeship (PWA) rules as the other clean energy credits, set out in Treas. Reg. 1.45-7Treas. Reg. 1.45-7Treasury regulations, eCFR and 1.45-8 (see the prevailing wage requirement and the apprenticeship requirement).

Base amount vs increased amount

For 45Y, the statute sets a base of 0.3 cents per kWh and an alternative amount of 1.5 cents, both adjusted for inflation. The 2026 Federal Register notice (published September 4, 2026) gives the 2026 figures: the base amount “is 0.6 cents (or $0.006)”, and the PWA amount “is 3.1 cents (or $0.031)”, for electricity sold, consumed or stored in calendar year 2026. For 48E, the statute sets a base rate of 6 percent, and 30 percent for a facility that meets the wage rule and, for its construction, the apprenticeship rule. Energy storage technology has the same 6% and 30% split.

CreditBase (no PWA)With PWA or an exception2026 figures
45Y production0.3 cents per kWh, inflation adjusted1.5 cents per kWh, inflation adjusted0.6 vs 3.1 cents per kWh
48E investment (facility)6% of qualified investment30%6% vs 30% (not inflation adjusted)
48E investment (energy storage)6%30%6% vs 30%

Because the increase is fivefold, owners usually write PWA into the EPC contract and every subcontract as a project requirement. Energy community and domestic content bonuses are separate and are outside this page.

Getting the 5x without meeting PWA

Two exceptions give the higher amount without the wage and apprentice tests. First, a facility “with a maximum net output of less than 1 megawatt (as measured in alternating current)” (for 48E storage, a capacity of less than 1 megawatt). Second, a facility whose construction began before January 29, 2023, the date 60 days after Notice 2022-61 was published; the 2026 amounts notice confirms the January 29, 2023 date in its first footnote. A facility that uses either exception does not file Form 7220. Details are on the bonus credit and exceptions page.

2026 status after P.L. 119-21

Public Law 119-21, enacted July 4, 2025, did not change the PWA rules for these credits. It changed which projects can get a credit at all. The current picture, as of November 2026:

ProjectRuleSource
Wind or solar, construction began by July 4, 2026No placed-in-service deadline from the 2025 law; continuity safe harbor of 4 calendar yearsP.L. 119-21 secs. 70512(l)(4), 70513(g)(5); Notice 2025-42
Wind or solar, construction began after July 4, 2026No credit if placed in service after December 31, 202745Y(d)(4); 48E(e)(4)
Energy storage, including at a wind or solar siteNot subject to the wind and solar termination48E(e)(4)(C)
Other zero-emission technologiesFull credit for construction beginning through 2033; 75% in 2034, 50% in 2035, none after45Y(d); 48E(e)
Construction began after December 31, 2025No credit if construction includes material assistance from a prohibited foreign entity45Y(b)(1)(E); 48E(b)(6), (c)(3)
Taxpayer is a specified foreign entity or foreign-influenced entityNo credit, tax years beginning after July 4, 202545Y(g)(13); 48E(d)(6)
Residential wind or solar leased to a third partyNo credit45Y(h); 48E(i)

A penalty rides on the material assistance rule, separate from PWA. IRM 20.1.5.10(1) says “The penalty applies when there is a substantial understatement of income tax due to the disallowance of a credit under section 45X, 45Y, or 48E by reason of overstating the material assistance cost ratio”; it is 20 percent of the understatement (20.1.5.10(4)) for tax years beginning after July 4, 2025 (20.1.5.10(5)). The general accuracy penalty is covered on TaxProc's accuracy-related penalty page.

Wind and solar: the July 4, 2026 deadline

The 2025 law added 45Y(d)(4) and 48E(e)(4): the credit “shall not apply with respect to any applicable facility placed in service after December 31, 2027” for wind and solar. That cutoff applies only to facilities that begin construction after July 4, 2026. Notice 2025-42 says “The credit termination date applies to applicable wind and solar facilities the construction of which begins after July 4, 2026”. A wind or solar facility that began construction by that date keeps the credit without the 2027 deadline, as long as it maintains a continuous program of construction. The notice's continuity safe harbor is met if the facility is placed in service within four calendar years after the year construction began.

For this deadline, Notice 2025-42 narrowed how construction may begin. For facilities that had not begun construction before September 2, 2025, the Physical Work Test “is the sole method that a taxpayer may use for these purposes”; the 5% cost safe harbor survives only for solar facilities of 1.5 MW AC or less. The test looks at the nature of the work, not its amount or cost: on-site, physical work of a significant nature begins with things like excavation for the foundation or setting anchor bolts. Read Notice 2025-42 in IRB 2025-36 for the full rules.

A PWA point follows from this. Physical work that starts the construction clock on or after January 29, 2023 is construction work, so the laborers and mechanics doing it must be paid prevailing wages and their hours count in the apprenticeship labor hours. Owners who rushed early site work to meet July 4, 2026 should check that those early crews were covered by PWA contract terms and payroll records.

Storage, geothermal, hydro, nuclear and other technologies

For non-wind, non-solar facilities and all energy storage, the phase-out is tied to an "applicable year," which the 2025 law fixed as calendar year 2032. Under 45Y(d)(2), the credit is 100% for construction beginning in the first year after 2032, 75% in the second year, 50% in the third, and 0% after that. In plain terms: storage, geothermal, hydropower, nuclear and similar projects that start construction in 2026 can still earn the full 5x amount if they meet PWA. Facilities that begin construction after December 31, 2025 must also clear the prohibited foreign entity material assistance rules; IRS Notice 2026-15 (February 12, 2026) gives interim safe harbors and, per the IRS release, applies to facilities “the construction of which begins after Dec. 31, 2025”.

One statutory wrinkle: new 48E(j), for qualified fuel cell property whose construction begins after December 31, 2025, sets the rate at 30 percent and says “such percentage shall not be increased or otherwise adjusted by any other provision of this section”. We have not seen IRS guidance on how that sentence interacts with the 6% base and PWA increase. If you build fuel cells, ask your adviser before assuming PWA does or does not apply.

Which PWA rules apply

45Y borrows the 45 rules directly: 45Y(g)(9) and (10) apply rules similar to 45(b)(7) for wages and 45(b)(8) for apprenticeship. 48E borrows the investment credit version: 48E(d)(3) applies rules similar to 48(a)(10) for wages, and 48E(d)(4) the 45(b)(8) apprenticeship rules.

Rule45Y48E
Prevailing wage during constructionYesYes
Prevailing wage on alteration or repairAny year of the 10-year credit period, tested year by year5 years after placed in service
If a later year failsNo bonus for that year unless curedRecapture of the bonus: 100% in year 1, down 20 points a year
Apprenticeship (12.5% or 15% of hours, ratio, participation)Construction onlyConstruction only
Correction and penalty cure45(b)(7)(B): back pay, interest, $5,000 per workerSame, through 48(a)(10)(B)

For 48E, IRC 48(a)IRC 48Internal Revenue Code, Cornell LII(10)(A) covers “for the 5-year period beginning on the date such project is originally placed in service, the alteration or repair of such project”. The recapture rules are in Treas. Reg. 1.48-13(c)Treas. Reg. 1.48-13Treasury regulations, eCFR, which the Form 7220 instructions cite together with 1.48E-3(e). Apprentice hours are 15% of total labor hours for construction that began after 2023 (see the labor hours calculator). Routine maintenance after the facility is placed in service is not covered, but repairs are. If something goes wrong, see correction and penalties.

What to file

  1. 45Y: claim the credit on Form 7211, Clean Electricity Production Credit. The Form 7211 instructions say that if you qualify for the increased amount for meeting PWA, “you must file Form 7220”, Prevailing Wage and Apprenticeship (PWA) Verification and Corrections, for each qualified facility.
  2. 48E: claim the credit on Form 3468, Part V, and attach Form 7220 for each facility or energy storage technology that began construction on or after January 29, 2023 and uses the PWA increase.
  3. After the placed in service year, file Form 7220 again each year of the alteration and repair period (10 years for 45Y, 5 for 48E), or attach the signed no-alterations statement.
  4. Elective pay or transfer: register each property in Energy Credits Online first and enter the registration number on Form 7220, line 1, the same number as on the credit form and Form 3800, Part III. “A registration number is valid only for the tax year for which it was obtained.” For 45Y, that means renewing it each year of the 10-year period. “Changes with respect to one or more credit properties, including changes in ownership, require an amended registration to reflect the new facts.” (Form 3800 instructions; IRM 21.7.4.4.9.5(5).) A number is not an approval of the credit: see elective pay and PWA.
  5. Report any PWA penalties and 48E recapture on Form 4255.

When a clean energy account is created in the IRS portal, the IRS sends the business CP 199, which names the person who registered (IRM 21.3.1.7.26(1)). If nobody at your company did, IRM 21.3.1.7.26(2) gives the contact for the IRS's fraud office: “SBSECleanEnergyFraud@IRS.gov”.

Keep the payroll and apprentice records described on the PWA records page. The statute is at 26 U.S.C. 45Y and 26 U.S.C. 48E; for the year by year status of every credit, see which credits carry the wage rules in 2026.

Questions filers ask

Is the 45Y or 48E prevailing wage bonus still available in 2026?

Yes. The 2025 law did not change the PWA rules. Projects that can still claim 45Y or 48E (storage, geothermal, hydro, nuclear and others, plus wind and solar that began construction by July 4, 2026 or are placed in service by the end of 2027) get 5x only if they meet PWA or an exception.

Does a solar project under 1 MW need prevailing wages?

No. A facility with a maximum net output of less than 1 MW AC gets the higher amount without the PWA tests. It must still meet the wind and solar deadlines.

We started site work in June 2026. Did that work need prevailing wages?

If construction began on or after January 29, 2023 and you claim the 5x amount, yes. Laborers and mechanics on the physical work that began construction are covered, and their hours count for the apprentice percentage.

Do O&M crews on a 45Y wind farm need prevailing wages?

Repairs and alterations during the 10-year credit period, yes. Routine maintenance such as inspections, cleaning and filter changes is not covered.

What happens if a 48E project fails prevailing wage in year 3?

Unless you make the correction and penalty payments within 180 days of an IRS final determination, 60% of the bonus is recaptured. The base 6% credit is not affected by that rule.

Is battery storage at a solar farm cut off after 2027?

No. 48E(e)(4)(C) says the wind and solar termination does not apply to energy storage technology placed in service at such a facility.