The checker asks about federal money, the owner and the state, and clean energy credits at the increased amount. Each points to a different rule set, and the result lists every one your answers point to. It is a starting point, not a coverage ruling. The federal, state or IRS guide walks through the same questions in more depth.
The federal questions
The Davis-Bacon Act covers “every contract in excess of $2,000, to which the Federal Government or the District of Columbia is a party, for construction, alteration, or repair, including painting and decorating, of public buildings and public works” (40 U.S.C. 3142(a)). That is the direct federal contract.
Most covered work is not a direct federal contract. It is paid for by federal grants, loans or guarantees under other laws that adopt the Davis-Bacon standards, the Related Acts. The regulation puts the contract clauses in contracts for work “financed in whole or in part from Federal funds or in accordance with guarantees of a Federal agency” when one of those laws applies (29 CFR 5.5(a)). Each Related Act sets its own scope, so the checker says "may apply" for assistance. See Davis-Bacon Related Acts and Davis-Bacon coverage.
The state question
State laws are separate from Davis-Bacon, with their own thresholds, covered owners and rates. The checker's state data holds only states whose status we confirmed on the state's own statute and agency pages, and records only whether a state law is in force:
| Status in our data | States |
|---|---|
| State law in force (20) | Alaska, California, Connecticut, Delaware, Illinois, Maine, Maryland, Massachusetts, Michigan, Minnesota, Missouri, Montana, Nevada, New Jersey, New York, Ohio, Oregon, Pennsylvania, Virginia, Washington |
| No state law in force (9) | Arizona, Arkansas, Idaho, Indiana, Kentucky, Louisiana, New Hampshire, Oklahoma, Wisconsin |
| Not confirmed yet | Every other state and DC. The checker says to check the state agency. |
Two cases need care. In Virginia, the state rule applies to state agencies, and “any locality may adopt an ordinance requiring that, when letting contracts for public works paid for in whole or in part by funds of the locality”, so a city or county project is covered only where the locality has acted (Va. Code 2.2-4321.3). And some states with no law go further and bar local mandates: Arizona says local bodies “shall not by regulation, ordinance or in any other manner require public works contracts to contain a provision requiring the wages paid” meet a prevailing rate (A.R.S. 34-321). See the state laws hub.
The clean energy question
The IRS rules are tax rules, so they follow the credit, not the owner. For the increased credit or deduction amounts, the IRS lists two general requirements. The first: “Pay laborers and mechanics employed in construction, alteration or repair no less than applicable prevailing wage rates”. The second is to employ apprentices from registered apprenticeship programs for a set number of hours. The payoff is large: “taxpayers can increase the base amounts of these incentives by 5 times” (IRS prevailing wage and apprenticeship page).
The rates are Davis-Bacon rates. For the electricity production credit, the statute sets them at prevailing rates “as most recently determined by the Secretary of Labor, in accordance with subchapter IV of chapter 31 of title 40” (26 U.S.C. 45(b)(7)). Where no general wage determination fits, DOL takes supplemental requests; see supplemental wage determinations and the clean energy section.
When more than one applies
The rule sets stack: a privately owned solar project claiming the bonus credit carries the IRS rules with no public owner at all. Oregon's statute shows how an overlap is handled: if a project is subject to both, every contract must provide that workers “must be paid not less than the higher of the applicable state or federal prevailing rate of wage” (ORS 279C.830). Payroll reporting can double up too; the certified payroll due date tool shows the federal and state schedules side by side.
This checker is general information, not legal advice. Coverage turns on the contract, the funding agreement and agency rulings. Ask the contracting or funding agency about Davis-Bacon coverage and the state labor agency about state coverage.
Questions filers ask
Does Davis-Bacon apply if the federal money is only a small part of the project?
It can. The regulation reaches work financed “in whole or in part” from federal funds under a Related Act. The funding statute and the agreement decide; check them, or ask the funding agency.
Our project is private. Can prevailing wage rules still apply?
Yes, in two common cases: a private project that takes public money under a state law or a Related Act, and a clean energy project claiming the increased credit, where the IRS rules apply to the taxpayer whoever owns the site.
Why does the checker say my state is not confirmed yet?
We list a state only after confirming its status on the state’s own statute and agency pages. Until then, check with the state labor agency. The state laws hub links to them.
If both a state law and Davis-Bacon apply, which rate do I pay?
You must meet both. Some states say so in their statute: Oregon requires the higher of the state or federal rate on a project subject to both.