The Act reaches the 50 states, DC and the Northern Mariana Islands; some Related Acts also reach the territories. CWHSSA overtime adds on above $100,000. 40 U.S.C. 3142(a)40 U.S.C. 3142United States Code, Cornell LII; 29 CFR 5.229 CFR 5.2Code of Federal Regulations, eCFR and 5.5; DOL Fact Sheet 66C.
The statutory test
Coverage starts with one sentence in 40 U.S.C. 3142(a). The advertised specifications must state minimum wages for “every contract in excess of $2,000, to which the Federal Government or the District of Columbia is a party, for construction, alteration, or repair, including painting and decorating, of public buildings and public works”, where the work requires or involves the employment of mechanics or laborers. DOL breaks that sentence into separate elements, and a contract has to meet all of them.
| Element | What it means in practice | Where it is defined |
|---|---|---|
| More than $2,000 | Measured on the prime contract, not each subcontract | 40 U.S.C. 3142(a)40 U.S.C. 3142United States Code, Cornell LII; 29 CFR 5.5(a)29 CFR 5.5Code of Federal Regulations, eCFR |
| Federal government or DC is a party | Executive departments, agencies, instrumentalities and nonappropriated fund instrumentalities | 29 CFR 5.229 CFR 5.2Code of Federal Regulations, eCFR, “United States or the District of Columbia” |
| Construction, alteration or repair | All types of work on a building or work at the site of the work, including painting and decorating | 29 CFR 5.229 CFR 5.2Code of Federal Regulations, eCFR, “Construction, prosecution, completion, or repair” |
| Public building or public work | Carried on by authority of or with funds of a federal agency to serve the general public | 29 CFR 5.229 CFR 5.2Code of Federal Regulations, eCFR |
| Laborers or mechanics are employed | Workers whose duties are manual or physical | 29 CFR 5.229 CFR 5.2Code of Federal Regulations, eCFR, “Laborer or mechanic” |
The contracting agency makes the first call. DOL's Resource Book says “The contracting agency has the initial responsibility to determine whether a contract is covered by the DBRA”, and any doubt about coverage or the right wage determination goes to the Wage and Hour Division (WHD) Administrator for a ruling.
The $2,000 threshold
The dollar test is applied once, at the top of the contract chain. In DOL's words, “The $2,000 threshold for coverage applies to the amount of the prime contract, not to the amount of individual subcontracts.” Fact Sheet 66C makes the same point from the subcontractor's side: when a prime contract is covered, “every subcontract of any tier under that prime contract is also covered, regardless of the dollar value of the subcontract”.
So a $1,500 painting subcontract under a $40,000 covered prime contract is a Davis-Bacon job, and the painter's workers must be paid the wage determination rates and reported on certified payroll. The $2,000 figure is in the statute itself, and DOL's 2023 rule notes that comments asking to change it would require Congress to amend the statute.
A second threshold sits on top: the overtime clauses of the Contract Work Hours and Safety Standards Act (CWHSSA) go into covered contracts over $100,000 (29 CFR 5.5(b))29 CFR 5.5Code of Federal Regulations, eCFR. See Davis-Bacon overtime and the CWHSSA.
Direct federal construction contracts also carry Miller Act performance and payment bonds above a dollar line: more than $100,000 in 40 U.S.C. 3131(b)40 U.S.C. 3131United States Code, Cornell LII, and over $150,000 in FAR 28.102-1(a)FAR 28.102-1Federal Acquisition Regulation, acquisition.gov. The performance bond guarantees the prime's withheld payroll taxes. See Miller Act bonds and payroll taxes.
Construction, alteration or repair
The regulations define the phrase broadly. It covers all types of work done on a particular building or work at the site of the work by laborers and mechanics of a contractor or subcontractor. It includes altering, remodeling, onsite installation of items fabricated offsite, painting and decorating, some transportation and some demolition.
The term “building or work” is just as wide. The list in 29 CFR 5.229 CFR 5.2Code of Federal Regulations, eCFR runs from bridges and dams to sewers and airports, and the 2023 rule added “solar panels, wind turbines, broadband installation, installation of electric car chargers”. A contract can also be covered when it touches only a portion of a building or work, or installs equipment or components into one.
Mixed contracts. A contract does not have to be mainly about construction. DOL says “A prime contract is for construction as long as it requires more than an incidental amount of construction”. Factors include the nature of the contract, the skills and equipment used, whether the work changes the structure, and the cost of the construction work. That is how a supply contract that calls for installation, or a base support contract with reroofing task orders, picks up a Davis-Bacon component next to the Service Contract Act.
Repair or maintenance. Alterations and repairs are construction. Routine upkeep is not: the Resource Book says “routine maintenance and preventative work is a service covered by the SCA”, assuming the other SCA tests are met. The line is drawn task by task, so a hybrid contract can carry both rate types.
Demolition. Demolition is covered when it is itself an alteration or repair (asbestos or paint removal from a facility that stays up, for example), when covered construction is planned at the site in the same or a future contract, or when a statute says so. A standalone teardown with nothing planned after it is generally a service.
Public building or public work
A public building or public work is one whose construction is carried on by authority of or with funds of a federal agency “to serve the interest of the general public regardless of whether title thereof is in a Federal agency”. Federal ownership is a strong sign, but it is not required.
DOL also looks past the form of the deal. The Resource Book says WHD will treat “any expenditure or transfer of funds or an asset of financial value directly or indirectly in exchange for construction” as meeting this element, and that a contract for construction does not have to be a procurement contract or one subject to the FAR. Leases that contemplate publicly funded construction and land swaps for new government facilities are its examples. For leases, All Agency Memorandum 176 lists the factors: lease length, government control of the design and inspection, private versus public use, whether the rent pays for the construction, and whether the deal was written as a lease to avoid the Act.
Where the Act applies
The Davis-Bacon Act itself reaches public buildings and works in the 50 states and the District of Columbia. DOL's Resource Book adds the Commonwealth of the Northern Mariana Islands under its covenant with the United States, and says “The DBA does not apply to federal construction contracts in Guam, Puerto Rico, the Virgin Islands or other territories.” Some Related Acts do reach construction in the territories, so a territorial project funded by a federal grant may still carry Davis-Bacon rates.
Federally assisted projects
Much Davis-Bacon work reaches contractors through federal assistance rather than a direct federal contract. Fact Sheet 66 says the Related Acts “include provisions that apply Davis-Bacon labor standards to most federally assisted construction”, through grants, loans, loan guarantees and insurance. Highway, transit, water, housing and school construction commonly arrive this way. Each Related Act has its own coverage words, and some have their own thresholds, so the test above is only the starting point. See Davis-Bacon Related Acts for the list and how to read your funding statute.
Clean energy tax credits are different. DOL says the Inflation Reduction Act is not a Davis-Bacon Related Act. The credits use their own IRS prevailing wage rules; see Clean energy credits. A project can have both if it also takes a federal grant or loan under a Related Act. If you are not sure which set applies, start with Federal, state or IRS: which prevailing wage rules apply.
What coverage triggers
Once a contract is covered, the labor standards clauses in 29 CFR 5.5 go into any contract over $2,000, in full or (for FAR contracts) by reference, and flow down to every subcontract. The main duties they create:
- Pay each laborer and mechanic at least the wage determination rate and fringe benefits for the classification of work actually performed, at least once a week.
- Post the wage determination and the Davis-Bacon poster (WH-1321) at the site where workers can easily see them.
- Submit certified payroll every week that covered work is performed. See who files certified payroll.
- Keep payroll and basic records for at least 3 years after all work on the prime contract is completed.
- Pay time and a half over 40 hours in a workweek if the contract is over $100,000 (CWHSSA).
- Insert the same clauses and wage determination in every lower-tier subcontract, and answer for the subcontractors' compliance.
The rates themselves come from the wage determination in the contract. See Wage determinations for how to read one and which modification applies.
If the clauses are missing
A covered contract sometimes goes out without the clauses or the wage determination. The 2023 rule tried to fix that with 29 CFR 5.5(e)29 CFR 5.5Code of Federal Regulations, eCFR, which made the clauses effective by operation of law. That paragraph was enjoined on June 24, 2024 and vacated in its entirety by the final judgment in AGC v. DOL, No. 5:23-cv-272-H (N.D. Tex.), Final Judgment, Doc. 108, June 24, 2026. Some DOL pages, including Fact Sheet 66C and the Resource Book coverage chapter, still describe operation of law as current; do not rely on them for that point.
The older post-award route was not part of the judgment. Under 29 CFR 5.6(a)(1)29 CFR 5.6Code of Federal Regulations, eCFR(ii) and 1.6(f), if a covered contract is signed without the clauses or the correct wage determination, the agency must add them by change order or supplemental agreement, or terminate and resolicit. Incorporation is retroactive to award (or the start of construction if there was no award) unless the Administrator directs otherwise, it must happen within 30 days of a request from the Administrator, and “The contractor must be compensated for any increases in wages resulting from incorporation of a missing contract clause.” More on the court case: The 2023 Davis-Bacon rule in 2026.
A coverage check
- Find the prime contract amount. Over $2,000? Then the dollar test is met for every tier.
- Who signed it or paid for it? A federal agency or DC means the Davis-Bacon Act. A state, city, housing authority or private owner using federal assistance means a Related Act may apply: find the funding statute.
- Is there more than an incidental amount of construction, alteration, repair, painting or decorating? Separate repair from routine maintenance task by task.
- Is the work in a state, DC or the Northern Mariana Islands? In another territory, check the Related Act.
- Read the contract for the 29 CFR 5.529 CFR 5.5Code of Federal Regulations, eCFR or FAR 52.222-6FAR 52.222-6Federal Acquisition Regulation, acquisition.gov clauses and a wage determination. If they are missing on a job you think is covered, raise it with the contracting officer in writing before work starts.
- Check state law too. A state prevailing wage law can apply to the same job: see State prevailing wage laws.
Questions filers ask
Is my $1,800 subcontract covered?
Yes, if the prime contract is over $2,000 and covered. The threshold applies to the prime contract, and DOL says every subcontract under a covered prime is covered regardless of its dollar value.
Does Davis-Bacon apply to a building the government leases rather than owns?
It can. Ownership is not required. DOL looks at whether the construction is carried on by authority of or with funds of a federal agency, and for leases it applies the factors in All Agency Memorandum 176, such as lease length, government control and whether the rent pays for the construction.
Is maintenance work covered?
Routine and preventive maintenance is generally a service under the Service Contract Act. Alteration and repair, including renovation, is construction under Davis-Bacon. On a mixed contract the line is drawn for each task order or work order.
Does Davis-Bacon apply in Puerto Rico?
The Davis-Bacon Act itself does not apply to federal construction contracts in Puerto Rico, Guam, the Virgin Islands or other territories (the Northern Mariana Islands are the exception). Some Related Acts do apply there, so check the statute behind the funding.
Do clean energy projects claiming the IRA credits follow Davis-Bacon?
Not as a Related Act. DOL says the Inflation Reduction Act is not a Davis-Bacon Related Act; the credits have their own IRS prevailing wage and apprenticeship rules. A project that also takes a federal grant or loan under a Related Act must meet both.
What if the contract has no Davis-Bacon clauses but should?
Raise it with the contracting officer. Under 29 CFR 5.629 CFR 5.6Code of Federal Regulations, eCFR and 1.6(f) the agency must add the clauses and wage determination, generally retroactive to award, and compensate the contractor for any wage increase. The 2023 operation-of-law paragraph, 5.5(e), was vacated on June 24, 2026.