Calculator

Apprentice request deadlines for the good faith effort exception

To use the good faith effort exception, a request for apprentices must reach a registered program 45 days before the requested start (14 days for later requests to the same program), and a program that does not reply within 5 business days is treated as denying it. Enter your dates to see each deadline. General information, not tax advice.

Updated November 21, 2026Sources 26 U.S.C. 45(b)(8)(D)(ii); Treas. Reg. 1.45-8(f)(1); T.D. 9998 preamble; IRS PWA FAQ; 5 U.S.C. 6103Privacy runs in your browser; nothing you enter is sent or stored
The date the email was sent, or the delivery date on the registered mail receipt.
When the apprentices are asked to start work.
The last day of the requested period.
45 days ahead for a first request; 14 for later ones.

What the tool works out

This is general information, not tax advice. A taxpayer that cannot get apprentices can still be treated as meeting the apprenticeship rules under the good faith effort exception, if its request to a registered apprenticeship program meets the timing in Treas. Reg. 1.45-8(f)(1). The tool shows the last day to send the request, the reply window, and how long a denied or unanswered request covers.

45 days for a first request, 14 for later ones

The regulation sets the lead time. The initial request to a program “must be made no later than 45 days before the qualified apprentices are requested to start work”. After that, requests to the same program “must be made no later than 14 days before the qualified apprentices are requested to start work”. The program's area must cover the site and it must train the occupations needed. “Such request must be in writing and sent electronically or by registered mail.” The apprentice request letter template lists what it must say.

The 5 business day reply window

The statute treats the exception as met if the program “fails to respond to such request within 5 business days after the date on which such registered apprenticeship program received such request” (26 U.S.C. 45(b)(8)(D)(ii)). The regulation says the receipt date “is determined by the date the electronic request is sent to the registered apprenticeship program or the date of delivery shown on a receipt from the registered mail delivery”, and that a late or missing reply means the request “is deemed to be denied”.

Neither text defines a business day. The tool counts Monday to Friday from the day after receipt and by default skips the legal public holidays in 5 U.S.C. 6103(a), such as “Thanksgiving Day, the fourth Thursday in November.” For a Saturday holiday it skips the Friday before (“the Friday immediately before is a legal public holiday” for weekday workers); for a Sunday holiday, the Monday after. Skipping more days only makes the date later, the safe side. A reply that lands in a spam folder still counts (Example 1 of 1.45-8(f)(1)(ii)).

The taxpayer “does not need to follow up with the registered apprenticeship program after the initial request”. On a partial offer, you “must accept the qualified apprentices offered in response to the request” to keep the exception for the rest.

365 days, not 120: how long a request covers

A denied or unanswered request covers the taxpayer “for the period described in the request but not exceeding 365 days (366 days in case of a leap year)” (1.45-8(f)(1)(i)(A)(2))Treas. Reg. 1.45-8Treasury regulations, eCFR. For a longer job, send another request; “There is no limit on the number of requests”.

In the regulation's Example 5, a request for apprentices from September 1, 2025 to December 31, 2026 was denied; it covered the taxpayer “for the period beginning September 1, 2025, and ending August 31, 2026”. The tool counts the same way, from the requested start date. The IRS PWA FAQ words it as 365 days “from the date of the request”; where that gives an earlier date, the tool shows it as a cautious reading.

Older articles mention a 120-day rule. Under the 2023 proposed regulations, taxpayers “would be required to submit an additional request for apprentices every 120 days after a denial”. The final regulations dropped it: “the maximum duration of a request for qualified apprentices is 365 days (366 days in case of a leap year)” (preamble to T.D. 9998, issued by Douglas W. O'Donnell, Deputy Commissioner, and approved June 9, 2024 by Aviva R. Aron-Dine, Acting Assistant Secretary of the Treasury (Tax Policy)).

Checked against the regulation's examples

Example in 1.45-8(f)(1)(ii)Dates enteredTool result
Example 4Request Nov 15, 2024; start Jan 2, 2025; end June 30, 2025Send by Nov 18, 2024: on time; reply due Nov 22, 2024; covered through June 30, 2025
Example 5Request June 1, 2025; start Sept 1, 2025; end Dec 31, 2026Send by July 18, 2025: on time; covered through Aug 31, 2026; new request needed for Sept 1, 2026 on

Covered hours count as apprentice hours in the labor hours calculator and cut the $50 per hour penalty in the penalty estimator. The good faith effort guide covers the rest, including denials that do not qualify. One intentional disregard factor asks whether the taxpayer “required contractors and subcontractors to forward to the taxpayer requests to registered apprenticeship programs within five business days of when requests were made”.

Keep the request, the proof of sending or delivery, and every reply: the records rules in 1.45-12 expect them, and Form 7220 asks about good faith requests.

Questions filers ask

How long does the apprenticeship program have to answer?

Five business days after it receives the request. Receipt is the date the email is sent, or the delivery date on the registered mail receipt. With no substantive reply by then, the request is deemed denied.

Does a phone call count as a request?

No. The request must be in writing, sent electronically or by registered mail.

Do we still have to re-request apprentices every 120 days?

No. The 120-day rule was in the 2023 proposed regulations. The final regulations let a denied or unanswered request cover up to 365 days (366 with a leap day), and a new request is needed only for time beyond that.