Nebraska prevailing wage law

Nebraska has no prevailing wage law of the usual kind: no state rates, no agency program and no certified payroll. What it has is a 1939 law, Neb. Rev. Stat. 73-102 to 73-104, under which public bodies make every bidder on public works file a statement that it complies with fair labor standards. Federal Davis-Bacon still applies to federal and federally assisted work in Nebraska.

Updated November 21, 2026Sources Neb. Rev. Stat. 73-101 to 73-104; 40 U.S.C. 3142; DOL Fact Sheet 66

At a glance

Nebraska is a special case, not a no-law state and not a full prevailing wage state. Its statute sets a standard but no machinery. There is no agency that publishes rates, no payroll filing and no penalty schedule. The duty falls on each state agency, county, city, school district or other public body when it lets a public works contract. The four sections were read on the Nebraska Legislature's official statutes site on November 21, 2026.

ItemNebraska ruleSection
Who must actState and local governing authorities and purchasing agents awarding public works73-102
Bidder's dutyFile a statement that it complies, and will comply, with fair labor standards73-102
Contract termA provision that fair labor standards will be maintained73-102
StandardWages and conditions paid by at least 50 percent of contractors in the same field73-104
EnforcementA public hearing showing noncompliance disqualifies the low bid73-103
Rates, payroll, agencyNone73-101 to 73-104

Which projects are covered

Section 73-102 applies to all governing authorities of the state and its subdivisions, and every person acting as their purchasing agent. In awarding public works contracts they must “require all contractors bidding on public works to file with such authority a statement that he is complying with, and will continue to comply with, fair labor standards” in its business and on the contract. Each public works contract must also say that fair labor standards will be maintained.

There is no dollar threshold in the text. There are two carve-outs:

Carve-outRuleSection
Bodies with their own labor termsThe section does not apply to authorities that set hours, rates of pay and conditions of employment in their own public works contracts73-102
Alternative delivery actsSections 73-101 to 73-106 do not apply to the State Building Construction Alternatives Act, the State Park System Construction Alternatives Act, the Public Water and Natural Resources Project Contracting Act, or sections 39-2808 to 39-282373-101

The first carve-out reads: “This section shall not apply to such governing authorities that prescribe, in the terms of their contracts for public works, provisions governing the hours of labor, rates of pay, and conditions of employment.” So a city that writes its own wage terms into a contract uses those terms instead of the statement. The second comes from 73-101, which says “Sections 73-101 to 73-106 shall not apply to the State Building Construction Alternatives Act” and the other acts listed above.

There is also a cost limit on state agencies. Section 73-102 says no state agency or department “shall make any requirements, because of the provisions of sections 73-101 to 73-104” that will increase the cost to the state of merchandise, materials, supplies or services.

Rates

Nebraska publishes no rates. The standard is defined in 73-104: fair labor standards means “such a scale of wages and conditions of employment as are paid and maintained by at least fifty percent of the contractors in the same business or field of endeavor” as the contractor filing the statement. It is a comparison against your own industry, measured by what half of your competitors pay, not a list of rates by craft and county.

The official annotations show how the courts read it. The note to 73-104 summarizes Philson v. City of Omaha (1958): “Provision for payment of a sum no less than going wage is a proper fair labor standard”, while payment of a fixed sum irrespective of the going wage is not. The note to 73-101 cites the same case for the point that a city ordinance requiring a minimum wage on public contracts did not implement the statute. If a Nebraska owner puts its own wage clause in your contract, that clause is a contract term you must follow.

Read the statute for what it is: it sets no rates by craft or county, no payroll filing and no agency. It requires a bidder statement and a contract clause, measured against what at least half of the bidder's own industry pays.

Certified payroll

Nebraska law has no certified payroll filing for public works. The only paper the statute requires from a contractor is the bidder's statement under 73-102. Federal weekly certified payroll still applies to any Nebraska job covered by Davis-Bacon or a Related Act: see who files certified payroll and the WH-347. Your public works contract may also ask for payroll records; read it.

Contractor registration and fees

We found no prevailing wage registration or fee in Neb. Rev. Stat. 73-101 to 73-104 (as of November 2026). Before you sign a subcontractor on a federally assisted job, check that its name and tax ID match its W-9; 1099-NEC reporting for subcontractors is covered at tincompliance.com.

Apprentices

The statute says nothing about apprentices. On Davis-Bacon work in Nebraska, the federal registered apprentice rules apply: see Davis-Bacon apprentices.

Penalties, debarment and worker claims

The statute's only sanction is losing the bid. Under 73-103, if interested parties show in a public hearing, to the awarding authority's satisfaction, that a bidder who filed the statement has not complied with fair labor standards, that showing “shall be the basis for the disqualification of the low bid”. The authority then lets the contract to the next lowest responsible bidder. There is no fine, debarment list or worker lawsuit in these sections.

Recent changes

The fair labor standards sections, 73-102 to 73-104, date from Laws 1939, c. 55, with no later amendments in their source notes. Section 73-101, the bid opening rule that carries the carve-out list, was amended by Laws 2024, LB461, and Laws 2025, LB180 and LB660. We did not read those bills, so we do not say which part of 73-101 each changed. No bill creating a Nebraska prevailing wage program was found in the statute text as of November 2026.

State law and Davis-Bacon on the same job

Federal law fills most of the gap. The Davis-Bacon Act covers every federal contract over $2,000 for construction of public buildings and public works, and the Related Acts carry the same rules to many federally assisted projects. In Nebraska those jobs use the federal wage determination for the county and federal weekly certified payroll. DOL notes that contractors on these projects “may also be subject to additional prevailing wage and overtime pay requirements under State (and local) laws”; in Nebraska, the state layer is the bidder statement and any wage clause the owner adds.

Clean energy projects have a third set of rules. A taxpayer claiming the increased credit must ensure that laborers and mechanics “are paid wages at rates not less than the prevailing rates for construction, alteration, or repair of a similar character in the locality in which such facility is located”, using the rates most recently determined by the Secretary of Labor. That applies in Nebraska like anywhere else: see the clean energy section. To sort out which rules reach your project, use which prevailing wage rules apply and Davis-Bacon coverage.

Questions filers ask

Does Nebraska have a prevailing wage law?

Not in the usual sense. There are no state rates, agency or payroll rules. A 1939 law requires public works bidders to file a statement that they comply with fair labor standards.

What does fair labor standards mean in Nebraska?

The wages and conditions paid and maintained by at least 50 percent of the contractors in the same business or field as the bidder (Neb. Rev. Stat. 73-104).

What happens if a Nebraska bidder does not meet fair labor standards?

If shown at a public hearing, the low bid is disqualified and the contract goes to the next lowest responsible bidder (73-103).

Do I file certified payroll on a Nebraska public works job?

Not under state law. Federal weekly certified payroll applies if Davis-Bacon or a Related Act covers the job, and your contract may require records.

Does Davis-Bacon apply in Nebraska?

Yes, on federal contracts over $2,000 for public buildings and public works, and on federally assisted projects under the Related Acts.

Sources