Montana prevailing wage law

Montana requires the standard prevailing wage on public works contracts over $25,000: construction contracts let by the state, counties, cities, school districts and other political subdivisions, and contracts for listed nonconstruction services let by those bodies other than school districts. The Montana Department of Labor and Industry (DLI) sets the rates each year from its own survey and union agreements. There is no routine certified payroll filing, but you must keep records ready to certify and produce them within 5 days if DLI asks.

Updated November 21, 2026Sources MCA 18-2-401 to 18-2-432 (Montana Code Annotated 2025); Montana DLI Prevailing Wage Rates page

At a glance

Montana's law sits in the public contracts title of the code, not the labor title. It is short and practical: the public body puts the rates in the bid specification and the contract, the contractor posts them and pays them, and DLI steps in when someone complains. The rules below come from the 2025 Montana Code Annotated sections and the DLI rates page, read on November 21, 2026.

ItemMontana ruleWhere it comes from
Who must payContractors, subcontractors and employers on public works contractsMCA 18-2-401, 18-2-403
Dollar thresholdTotal contract cost over $25,000 (as of November 2026)MCA 18-2-401(11)
Who sets ratesDLI, from an annual survey and collective bargaining agreementsMCA 18-2-402, 18-2-413 to 18-2-415
Rate areasUp to five districts for building and nonconstruction; statewide for heavy and highwayMCA 18-2-403, 18-2-411
Certified payrollOnly when DLI requests it after a complaint; due within 5 daysMCA 18-2-423
Records keptAt least 3 years after your work on the project endsMCA 18-2-422
Worker remedyWages owed plus $25 a day for each day underpaidMCA 18-2-407

Which projects are covered

The trigger is a "public works contract." MCA 18-2-401 defines it as a contract for construction services let by the state, a county, municipality, school district or political subdivision, or for nonconstruction services let by the state, a county, municipality or political subdivision, “in which the total cost of the contract is in excess of $25,000”. Contracts that the Department of Public Health and Human Services signs for human services are excluded.

Construction services means building, heavy and highway construction and remodeling work. Engineering, superintendence, management, office and clerical work are not covered, and neither are consulting contracts, supply contracts with commercial suppliers or contracts with licensed professionals. Montana also covers a list of nonconstruction services on public property: building and road maintenance, custodial and security work, grounds maintenance, water and waste system operation, school and public transportation driving, food service, and equipment and appliance repair, among others. School districts that contracted out nonconstruction services before April 27, 1999 are outside the nonconstruction part.

Three edges of coverage matter on a job:

SituationMontana rule
Off-site shop built for the projectWork at a facility built or developed for a specific Montana public works project, located in the same prevailing wage district as the project or a contiguous one, counts as "special circumstances" and is covered (18-2-401(12), 18-2-403(2)).
Hauling materials“Transportation of goods, supplies, materials, and manufactured or fabricated items to or from the project location is not subject to payment of the standard prevailing rate of wages.”
Bond-financed private contractsA contract for a project costing more than $25,000 and financed with certain bonds under Title 17, ch. 5, part 15, or Title 90, ch. 5 or 7, must also carry the prevailing wage, unless the contractor has a collective bargaining agreement covering the work (18-2-403(7)).

Every public works contract must also tell the contractor to give preference to bona fide Montana residents. For how off-site work is treated elsewhere, see prevailing wage for off-site fabrication by state.

Rates

DLI publishes four rate books each year: building construction, heavy construction, highway construction and nonconstruction services. Section 18-2-402 sets the floor. When the part applies, the standard prevailing wage, including fringe benefits, is “the greater of the highest applicable rate of wages in the area for the particular work in question as negotiated under existing and current collective bargaining agreements or the rate determined by the applicable survey under this part”.

The survey runs every year. DLI's page says “The survey is open from early April through June 30th of each year.” For building construction, DLI surveys licensed electrical contractors and plumbers doing commercial work and registered construction contractors. It uses a weighted average wage for each craft unless at least 50 percent of the skilled workers get the same wage; in that case the higher of the union rate or the surveyed rate prevails (18-2-413). Heavy and highway rates are set statewide, and DLI may survey, adopt the U.S. Department of Labor's Davis-Bacon rates for Montana by rule, or combine the two (18-2-414).

Building construction and nonconstruction rates are set by district: the commissioner may divide the state into no more than five prevailing wage rate districts (18-2-411). Zone pay is measured in road miles from the dispatch city, the courthouse in Billings, Bozeman, Butte, Great Falls, Helena, Kalispell, Miles City, Missoula or Sidney closest to the job. Travel allowances run from the dispatch city or the worker's home, whichever is closer to the job. The contract and bid specification must state the rate for each job classification, including fringe benefits (18-2-422).

As of November 21, 2026, DLI posts revised 2026 rates, which it says supersede the rates published earlier, and draft 2027 rates for comment before November 15, 2026. Long jobs get a built-in raise. Any contract that calls for more than 30 months of work must include an adjustment 12 months after award and every 12 months after that; under 18-2-417, “The amount of the adjustment must be a 3% increase.” The increase is the contractor's cost, not the agency's.

Fringe benefits

Montana defines fringe benefits as health, welfare and pension contributions that meet ERISA, plus other bona fide programs approved by the U.S. Department of Labor. You can pay the full rate in cash, make irrevocable contributions to a qualifying plan, or combine the two, as long as the total is at least the standard rate including fringe benefits and travel allowances (18-2-412). A private contractor or subcontractor must file a copy of its fringe benefit plan with DLI. If the plan is an ERISA plan, its annual return is covered at form5500.org. For the federal approach to credits, see Davis-Bacon fringe benefits.

Certified payroll and records

Montana has no weekly or monthly certified payroll filing and no state payroll portal. Instead, the contract must require each contractor and employer to keep payroll records “in a manner readily capable of being certified for submission” under 18-2-423, for at least 3 years after its work on the project ends. Section 18-2-423 then sets the trigger and the clock:

  1. Pay hourly employees every week. Section 18-2-423 requires weekly pay on public works.
  2. Keep payroll records for every worker on the project in a form you can certify on short notice.
  3. If a complaint is filed, DLI may require certified copies of the payroll records for workers on the project.
  4. Once DLI asks, the contractor or subcontractor “shall provide the employee's payroll records to the department within 5 days of receiving the payroll request from the department”.
  5. If records are refused, the commissioner may issue subpoenas to compel them (18-2-424).

Because filing is on demand only, the 5 day turnaround is the real test. Contractors that keep a weekly payroll in a WH-347 style layout (see the WH-347 guide) can usually certify a copy the same day. For how Montana compares with states that require routine filing, see certified payroll by state.

Registration, bonds and posting

We found no separate prevailing wage registration or fee in part 4 (as of November 2026). Part 4 does refer to construction contractors registered under Title 37, chapter 45, the state's construction contractor registration, which we did not review for this page. The duties part 4 does set out are these:

DutyRule
Post the ratesPost a legible statement of all wages and fringe benefits in a prominent, accessible place on the project or staging area, no later than the first day of work and for the whole project (18-2-406).
Contract approvalPublic works contracts must be approved in writing by the legal adviser of the contracting county, municipal corporation, school district, assessment district or special improvement district before they are signed (18-2-404).
RetainageAt least $1,000 of the contract price must be withheld at all times until the contract ends (18-2-404).
Fringe plan copyFile a copy of your fringe benefit fund, plan or program with DLI (18-2-412).
No forced labor agreementThe state and political subdivisions may not require a project labor agreement or collective bargaining agreement as a condition of bidding or working on a public works contract (18-2-425).

Apprentices

Only an apprentice whose indenture agreement is registered with DLI under Title 39, chapter 6, or recognized by DLI as registered with another state's agency or the federal government, may be paid an apprentice rate. A registered apprentice gets the percentage of the standard prevailing wage set in the apprenticeship standards, and “The percentage amount applies to wage rates only and not to fringe benefits.” The full fringe benefit is owed. An apprentice whose agreement is not registered or recognized must be paid the full journey-level rate, including travel allowances, and the apprentice rate starts only on the date of registration with the sponsor. Montana's part 4 sets no apprentice utilization percentage. For the federal rules, see Davis-Bacon apprentices.

Penalties, debarment and worker claims

Underpayment triggers two forfeitures under 18-2-407. To the state, the contractor, subcontractor or employer forfeits a penalty of up to 20 percent of the delinquent wages plus fringe benefits, attorney fees, audit fees and court costs. To the worker, it “shall also forfeit to the employee the amount of wages owed plus $25 a day for each day that the employee was underpaid”. If not enough money is left on the contract, the commissioner may sue in district court within 90 days after the notice of completion is filed and the agency accepts the project.

OutcomeAmount or lengthSection
Underpayment, penalty to DLIUp to 20% of delinquent wages plus fringes, attorney fees, audit fees and court costs18-2-407(1)
Underpayment, owed to the workerWages owed plus $25 for each day underpaid18-2-407(1)
Any failure to comply with part 4$1,000 of the contract price retained as liquidated damages18-2-432(1)(a)
Failure from gross negligenceUp to an additional $10,000 retained18-2-432(1)(b)
Aggravated or willful labor standards violationIneligible for public works contracts and subcontracts for up to 3 years18-2-432(2)
Contract missing the required clausesThe duty to pay the prevailing wage shifts to the public contracting agency18-2-403(9)

Debarment reaches related firms. A contractor or subcontractor found to have aggravatedly or willfully violated the labor standards, and any firm in which it has a substantial interest, “is ineligible, for a period not to exceed 3 years after the date of the final judgment”, to receive public works contracts or subcontracts. A court hearing a case under part 4 may also enjoin the contractor from going ahead with a public works contract until the case is decided.

Workers keep their own claim. Section 18-2-407 says part 4 does not prevent an underpaid worker, or the commissioner on behalf of all underpaid workers, from suing for the wages due under the contract under Title 39, chapter 3, part 2.

Recent changes

The 2025 code shows that sections 18-2-413 (building construction rates) and 18-2-414 (heavy and highway rates) were amended by Chapter 644, Laws of 2025, according to each section's history note. We did not read the session law itself, so check the current text of those two sections before relying on an older summary of the rate method. On the rate side, DLI's page says the posted 2026 rates are revised rates that supersede the earlier 2026 publication, and DLI asked for informal comments on the 2027 draft rate books before November 15, 2026. For changes across all states, see the state law changes log.

State law and Davis-Bacon on the same job

Montana's statute answers part of this directly. Section 18-2-402 says “The provisions of this part do not apply in those instances in which the standard prevailing rate of wages is determined by federal law.” On federal-aid contracts, 18-2-403 also says part 4 may not be enforced in a way that conflicts with federal statutes that give a labor preference to honorably discharged veterans. For heavy and highway work, DLI may adopt the federal Davis-Bacon rates for Montana by rule, so the two schedules can match. If federal money is involved, start with Davis-Bacon coverage and which prevailing wage rules apply, and ask DLI's Prevailing Wage Compliance Specialists how the state part applies to your contract.

Questions filers ask

What is the Montana prevailing wage threshold?

A public works contract is covered when its total cost is over $25,000 (MCA 18-2-401, as of November 2026). The same figure applies to nonconstruction services contracts and to certain bond-financed projects.

Do I file certified payroll in Montana every week?

No. Montana has no routine filing. Keep records you can certify, and if DLI requests them after a complaint, deliver them within 5 days. Hourly workers must be paid weekly.

Are truck drivers delivering materials covered?

Hauling goods, supplies, materials and manufactured or fabricated items to or from the project location is not subject to the prevailing wage (MCA 18-2-403(6)).

My contract runs three years. Do the rates change?

Yes. A contract that calls for more than 30 months must raise the rates by 3 percent 12 months after award and every 12 months after that. The contractor bears the increase.

How are apprentices paid on Montana public works?

A registered apprentice gets the program's percentage of the wage rate plus the full fringe benefit. An unregistered apprentice gets the full journey-level rate.

Who do I call with a rate question?

Montana DLI's Employment Standards Division. Its rates page lists (406) 444-6543 and offers prevailing wage training sessions and videos.

Sources