Wage determinations

The four construction types: building, residential, highway, heavy

Every Davis-Bacon general wage determination is issued for a type of construction, and the rates differ by type. DOL uses four: building, residential, highway and heavy. The type follows the nature of the project, and a project with substantial work of a second type usually carries a second wage determination.

Updated November 21, 2026Sources 40 U.S.C. 3142(b); 29 CFR 1.2 and 1.6(b); Fact Sheet 66D; DOL Prevailing Wage Resource Book; All Agency Memoranda 130, 131, 236 and 251

Why the type matters

The Davis-Bacon Act ties rates to “projects of a character similar to the contract work”. DOL turns that phrase into categories. 29 CFR 1.229 CFR 1.2Code of Federal Regulations, eCFR defines the construction type as the general category the Administrator sets for publishing general wage determinations, and adds: “Types of construction may include, but are not limited to, building, residential, heavy, and highway.”

Two points from Fact Sheet 66D govern how you place a project. First, the project is all construction needed to complete the building or work, regardless of how many contracts there are, so long as the contracts are closely related in purpose, time and place. Second, you look at the nature of the project itself in a construction sense, “rather than who is employed on the project or how much they are paid”. The same electrician is paid from a building schedule on a school and from a heavy schedule on a water plant.

The four types

DOL's descriptions come from All Agency Memorandum (AAM) 130, as summarized in Fact Sheet 66D and the Resource Book:

TypeWhat it coversExamples
BuildingSheltered enclosures with walk-in access for housing persons, machinery, equipment or supplies, plus integral utilities, equipment, site preparation, incidental grading and pavingHospitals, shopping centers, banks, schools, apartment buildings over four stories
ResidentialConstruction, alteration or repair of single-family houses or apartment buildings of no more than four stories, plus integral site work and utilitiesSingle-family houses, townhouses, apartments of four stories or fewer
HighwayRoads, streets, highways, runways, taxiways, alleys, trails, paths, parking areas and similar projects, with integral site preparation and gradingStreet resurfacing, a new runway, a parking area not incidental to a building
HeavyProjects not properly classified as building, highway or residentialDredging, water and sewer lines, dams, major bridges, flood control; the Resource Book also lists solar and wind farms

Building construction does not require a place people live or work. Fact Sheet 66D says the structure need not be habitable, and “The installation of heavy machinery and/or equipment does not generally change the project's character as a building.” A pump house or an equipment shelter with walk-in access can be building construction.

Counting stories for residential work

The line between residential and building for apartments is four stories, so the floor count decides which wage determination applies. Fact Sheet 66D treats a lowermost floor as a story if any of these is true:

  1. It is primarily above exterior grade on one or more sides and at least 50 percent of it is living space or related non-residential use (laundry, recreation rooms, commercial use, corridors).
  2. It is primarily above exterior grade on two or more sides, with no percentage test.
  3. It contains the main entrance to the building.
  4. It is used for apartments in a way substantially similar to the upper floors.

Below-grade stories used for storage, parking or mechanical equipment are basements and do not count. A top floor not finished for living, as large as the story below, does count. A half-floor finished as living space inside the roof frame counts if it is at least half as large as the story below. An unfinished attic does not count, even if used for storage.

Heavy construction and its sub-schedules

Heavy is the catch-all. Fact Sheet 66D: “Heavy projects are those projects that are not properly classified as either” building, highway or residential. Because heavy covers so much, DOL may issue separate schedules for kinds of heavy work. The sample general decision DC20260001 (District of Columbia, heavy and highway) shows this inside one document: its power equipment operator rates come in three sets, one for heavy and highway construction, one for paving and incidental grading, and one for sewer, gas and water line construction, each with its own groups and rates. Read the headings to find the set that fits the work.

For clean energy projects, DOL's Inflation Reduction Act page says that for a utility-scale solar facility “the taxpayer should identify the heavy construction wage determination for the area in which the facility is being constructed”, and it says the same for wind. See supplemental wage determinations for clean energy projects.

Examples

These follow the DOL descriptions above. Close cases go to WHD.

ProjectLikely typeWhy
New school with its own parking lot and utility hookupsBuildingSite work, utilities and paving integral to a building are part of the building project
Five-story apartment buildingBuildingResidential stops at four stories
Three-story apartment building over a below-grade parking levelResidentialA below-grade parking level is a basement and does not count as a story
Resurfacing city streetsHighwayStreets and roads
Water main replacementHeavyWater and sewer line work; some areas have a separate schedule
Utility-scale solar farmHeavyDOL's IRA guidance and the Resource Book place solar farms in heavy

Mixed projects: one wage determination or two

29 CFR 1.6(b)(1)29 CFR 1.6Code of Federal Regulations, eCFR requires the solicitation and contract to “incorporate the applicable wage determination for each type of construction involved that is anticipated to be substantial”. Fact Sheet 66D and the Resource Book set out a two-question test:

  1. Is part of the project, in itself, a different category of construction? Preparatory work does not count: “preparatory site work is included within the same category as the overall project itself, even if it is performed under a separate contract”.
  2. If so, is that other work substantial? DOL's guidance treats it as substantial when the total cost of all work in that category exceeds 20 percent of total project cost or a dollar threshold. All Agency Memorandum 251 (August 15, 2025) set that dollar threshold at $3.3 million for 2025, up from $2.5 million. If the work is substantial, multiple wage determinations generally apply; if not, the other work is incidental and one wage determination applies.

AAM 251 states the test this way: “contracting agencies should generally apply multiple wage determinations when the cost of the construction in this different category exceeds either $3.3 million or 20% of the total project cost”. When the other work crosses either line, the agency should apply the second wage determination to the work in that category and the main wage determination to everything else (unless a third type also applies).

PeriodDollar threshold for a second wage determinationSource
1987 to 2020$1 millionAAM 251 (history)
December 20, 2020$2.5 millionAAM 236
2025$3.3 millionAAM 251 (August 15, 2025)

The figure now moves with construction prices. WHD adjusts it using the “seasonally adjusted Producer Price Index (PPI) for construction for government”, and the 2020 threshold adjusted that way “results in a monetary threshold of $3.3 million for 2025”. The 20 percent test did not change.

Fact Sheet 66D adds that “these numbers are only benchmarks”: WHD may approve a single wage determination in exceptional cases. AAM 251 keeps that door open where the other work is not significantly greater than $3.3 million or 20 percent of project cost and the agency can show that multiple wage determinations would not reflect local area practice or would otherwise be inappropriate. The agency asks WHD for the exception; the contractor does not.

Fact Sheet 66D (October 2023) and the Resource Book still show $2.5 million. AAM 251 is the later guidance, and it says “WHD will continue to re-evaluate annually whether additional updates to the monetary threshold are warranted”. Before relying on $3.3 million for a project bid after 2025, check the All Agency Memoranda list on SAM.gov for a newer memo.

When a contract carries more than one wage determination, the agency must say which work each one covers. The Resource Book stresses that this applies even when schedules for different types or counties are combined in a single document, as in the DC sample, which covers both heavy and highway work.

Who decides, and what contractors should do

The contracting agency picks the wage determinations and puts them in the bid documents (29 CFR 1.6(b)(1))29 CFR 1.6Code of Federal Regulations, eCFR. That does not take the contractor off the hook: each contractor and subcontractor has an “affirmative obligation to ensure that its pay practices are in compliance” with the Davis-Bacon labor standards (29 CFR 1.6(b)(2))29 CFR 1.6Code of Federal Regulations, eCFR. Questions about which wage determination applies go to WHD for resolution (29 CFR 1.6(b)(3))29 CFR 1.6Code of Federal Regulations, eCFR.

If the type looks wrong, raise it during the bid period. The Resource Book asks that type-of-construction disputes go to WHD before bid opening, and Fact Sheet 66D lists what the agency should send: a full project description and its major segments, a cost breakdown when more than one type may apply, any area practice evidence, interested parties' comments, and the agency's recommendation. A wrong wage determination found after award can be replaced retroactively (see which modification applies), which is costly for everyone. Coverage itself, whether Davis-Bacon applies at all, is a separate question covered in Davis-Bacon coverage.

Questions filers ask

Does installing heavy equipment make a building project heavy construction?

Generally no. Fact Sheet 66D says the installation of heavy machinery or equipment does not generally change a project's character as a building, and a structure need not be habitable to be building construction.

Can site clearing and grading carry its own wage determination?

Generally no. Fact Sheet 66D says preparatory site work is in the same category as the overall project, even under a separate contract.

When does a second type of work need its own wage determination?

When its cost exceeds 20 percent of total project cost or $3.3 million, the 2025 figure set by All Agency Memorandum 251 (it replaced $2.5 million). WHD may grant the agency an exception in close cases.

Is a four-story apartment building residential?

Yes, if it has no more than four stories under the counting rules in Fact Sheet 66D. Below-grade parking and unfinished attics do not count; a lowermost floor with the main entrance does.

Which type covers a solar or wind farm?

Heavy. DOL's Inflation Reduction Act guidance tells taxpayers to use the heavy construction wage determination for utility-scale solar and for wind facilities.

Who is responsible if the agency picked the wrong type?

The agency must correct it, and a contractor must be compensated for wage increases when a missing wage determination is added after award (29 CFR 1.6(f))29 CFR 1.6Code of Federal Regulations, eCFR. Raising the issue before bid opening avoids the problem.