TermWhat it means
Davis-Bacon Act (DBA)The 1931 federal law (40 U.S.C. 3141 to 3148)40 U.S.C. 3141United States Code, Cornell LII40 U.S.C. 3148United States Code, Cornell LII requiring prevailing wages on federal contracts over $2,000 for construction, alteration or repair of public buildings and public works. See coverage.
Related ActsFederal laws that attach Davis-Bacon labor standards to construction paid for with federal grants, loans, loan guarantees or insurance, such as the federal-aid highway laws.
DBRAShort for the Davis-Bacon and Related Acts together.
Davis-Bacon labor standardsIn 29 CFR 5.229 CFR 5.2Code of Federal Regulations, eCFR, the requirements of the DBA, the Contract Work Hours and Safety Standards Act (other than safety and health), the Copeland Act and the prevailing wage provisions of the Related Acts, plus the rules in 29 CFR parts 129 CFR part 1Code of Federal Regulations, eCFR, 3 and 5.
Public building or public workA building or work whose construction is carried on by authority of or with funds of a federal agency to serve the general public, whoever holds title (29 CFR 5.2)29 CFR 5.2Code of Federal Regulations, eCFR.
Building or workConstruction of all types, as opposed to manufacturing, supplying materials, or servicing and maintenance. The 5.2 list names bridges, highways, sewers and power lines and also “solar panels, wind turbines, broadband installation, installation of electric car chargers”.
Construction, alteration or repairAll types of work on a building or work at the site of the work by laborers and mechanics of a contractor or subcontractor, including painting, decorating, some demolition and some transportation (29 CFR 5.2)29 CFR 5.2Code of Federal Regulations, eCFR.
Site of the workThe primary construction site where the work will remain, secondary sites where a significant portion (a whole module) is built for the project, and dedicated support sites next to them such as job headquarters, tool yards and batch plants (29 CFR 5.2)29 CFR 5.2Code of Federal Regulations, eCFR.
Laborer or mechanicA worker whose duties are manual or physical, including apprentices and helpers. Not people whose duties are primarily administrative, executive or clerical. See laborers and mechanics.
EmployedAnyone doing laborer or mechanic duties on covered work, “regardless of any contractual relationship alleged to exist between the contractor and such person”. Paying a worker on a 1099-NEC does not change this (for the W-9 and 1099 side, see tincompliance.com).
Prime contractorThe party that contracts with the agency. Under 5.2 it also includes controlling shareholders or members, joint venturers, and a general contractor delegated to oversee all or nearly all of the construction.
SubcontractorAny contractor, at any tier, that agrees to perform or be responsible for part of a covered contract (29 CFR 5.2)29 CFR 5.2Code of Federal Regulations, eCFR.
Material supplierA business whose only work on the project is delivering materials from a facility that is not on the site and was not set up just for the project. A supplier is not a contractor, so its workers are not covered. Paragraph (2) of the 2023 definition was vacated by the AGC v. DOL final judgment of June 24, 2026.
Covered transportationHauling that counts as construction: trips entirely within the site, hauling a significant portion of the work between a secondary and primary site, and trips between a dedicated support site and the site. The 2023 provision covering truck drivers' onsite loading and unloading time was vacated on June 24, 2026.
Contracting agencyThe federal, state or local agency that enters into the contract or provides the federal assistance. It must put the clauses and wage determination in the contract.

Wage determination terms

TermWhat it means
Wage determination (WD)The list of basic hourly rates and fringe rates for each job class on one type of construction in one area. Under 5.2 the term “includes the original decision and any subsequent decisions revising, modifying, superseding, correcting, or otherwise changing the provisions of the original decision”. See how to read a WD.
General wage determinationA WD published on SAM.gov for a county or group of counties. It has no expiration date and stays valid until revised, superseded or canceled (29 CFR 1.6)29 CFR 1.6Code of Federal Regulations, eCFR.
Project wage determinationA WD issued for one project when no general WD fits. It is “initially issued will be effective for 180 calendar days from the date of such determinations” and is void if not used in that time.
ModificationA revision to a general WD, shown by a modification number. Which modification applies depends on bid opening, award and contract changes.
Type of constructionThe category a WD covers: building, residential, heavy or highway (29 CFR 1.2)29 CFR 1.2Code of Federal Regulations, eCFR.
AreaThe city, town, village, county or other civil subdivision where the work is done. Highway WDs may use state highway districts (29 CFR 1.2)29 CFR 1.2Code of Federal Regulations, eCFR.
Prevailing wage (federal)The rate paid to more than 50 percent of workers in a class; if none, the rate paid to the greatest number if at least 30 percent; otherwise a weighted average (29 CFR 1.2)29 CFR 1.2Code of Federal Regulations, eCFR.
Rate identifiersCodes on a WD showing where a rate came from: a union code (such as PLUM0198) for a prevailing union rate, UAVG for a weighted union average, SU for a single non-union rate or survey average, SA for a state-adopted rate. On the sample DC WD: “A UAVG rate will be updated once a year, usually in January”.
State-adopted rateA state or local rate that WHD adopts as the Davis-Bacon rate under the 2023 rule (29 CFR 1.3)29 CFR 1.3Code of Federal Regulations, eCFR.
ConformanceAdding a job class that is missing from the WD. The first criterion: “The work to be performed by the classification requested is not performed by a classification in the wage determination”. Requests often use form SF-1444. See conformance.
Supplemental wage determinationFor the IRS credits, a WD that DOL issues on request when no general WD covers the area or construction type.
SAM.govThe federal website where DOL posts Davis-Bacon and Service Contract Act wage determinations.

Pay and payroll terms

TermWhat it means
Basic hourly rateThe cash hourly rate on the WD, before fringe benefits. Overtime under federal law is figured on this rate, not on the fringe (40 U.S.C. 3142(e))40 U.S.C. 3142United States Code, Cornell LII.
Fringe benefitsThe second part of the prevailing wage: medical care, pensions, life and disability insurance, vacation and holiday pay, apprenticeship costs and similar benefits. If a plan you credit is an ERISA plan, it generally files its own Form 5500 (see form5500.org). See fringe benefits.
Bona fideA fringe plan that qualifies for credit: contributions to a trustee or third party, or the costs of an enforceable, financially responsible plan communicated in writing to workers (29 CFR 5.2)29 CFR 5.2Code of Federal Regulations, eCFR.
Cash in lieuPaying the fringe amount as extra cash wages instead of into a plan. Allowed under 40 U.S.C. 3142(d)40 U.S.C. 3142United States Code, Cornell LII.
AnnualizationSpreading a fringe plan's cost over all hours worked in the year, public and private, to find the hourly credit (29 CFR 5.25)29 CFR 5.25Code of Federal Regulations, eCFR.
Certified payrollThe weekly payroll a contractor or subcontractor submits on DBRA work, signed under a statement of compliance.
WH-347DOL's optional form for certified payroll. Its use is optional, but the weekly payroll information is not. See WH-347 instructions.
Statement of ComplianceThe signed certification on page 2 of the WH-347. False statements can be prosecuted under 18 U.S.C. 100118 U.S.C. 1001United States Code, Cornell LII.
Overtime (CWHSSA)On covered contracts over $100,000, pay “at a rate not less than one and one-half times the basic rate of pay, for all hours worked in excess of 40 hours in the workweek” (40 U.S.C. 3702)40 U.S.C. 3702United States Code, Cornell LII.
KickbackForcing a worker to give back part of the wage. The Copeland Act makes it a crime to induce a worker “to give up any part of the compensation to which he is entitled under his contract of employment” (18 U.S.C. 874)18 U.S.C. 874United States Code, Cornell LII.

Apprentices and helpers

TermWhat it means
ApprenticeA worker individually registered in a bona fide apprenticeship program registered with DOL's Office of Apprenticeship or a recognized State Apprenticeship Agency, or in the first 90 days of certified probationary employment (29 CFR 5.2)29 CFR 5.2Code of Federal Regulations, eCFR. Only registered apprentices may be paid below the journeyworker rate.
RatioThe number of apprentices allowed per journeyworker under the registered program. Apprentices above the ratio must be paid the full journeyworker rate.
HelperA separate class on a WD only when its duties are clearly defined and distinct, using helpers is an established practice in the area, and the helper is not an informal trainee (29 CFR 5.2)29 CFR 5.2Code of Federal Regulations, eCFR.

Enforcement terms

TermWhat it means
WithholdingThe agency holding back contract payments to cover unpaid wages (40 U.S.C. 3142(c)(3); 29 CFR 5.9)40 U.S.C. 3142United States Code, Cornell LII29 CFR 5.9Code of Federal Regulations, eCFR. Cross-withholding takes the money from another contract held by the same prime contractor.
Back wagesThe difference between what a worker was paid and what the WD required, owed to the worker.
Liquidated damagesUnder CWHSSA, a set amount for each worker for each calendar day the worker was required or permitted to work over 40 hours without the overtime pay, owed to the government on top of the unpaid overtime (40 U.S.C. 3702(c))40 U.S.C. 3702United States Code, Cornell LII.
DebarmentA bar from federal contracts. DOL lists “debarment from future contracts for a period of three years” as a sanction for Davis-Bacon violations.
WHDThe U.S. Department of Labor's Wage and Hour Division, which issues WDs and enforces the DBRA.

IRS clean energy terms

TermWhat it means
PWAPrevailing wage and apprenticeship: the two requirements for the increased amount of the clean energy credits. See clean energy credits.
Increased credit amountThe bonus amount. For the production credit, the base credit “shall be equal to such amount multiplied by 5” when the requirements are met (IRC 45(b)(6))IRC 45Internal Revenue Code, Cornell LII.
Qualified facilityThe facility the credit is claimed for. Everyone who builds, alters or repairs it is covered, at every tier.
One megawatt exceptionFacilities under 1 megawatt of output can get the increased amount without meeting PWA, for the credits that offer it.
Beginning of construction exceptionFacilities whose construction began before January 29, 2023 can get the increased amount without meeting PWA, for the credits that offer it.
Correction payment and penaltyA way to cure underpayment: pay the worker the shortfall plus interest, and pay the IRS a penalty of $5,000 per underpaid worker (IRC 45(b)(7)(B)IRC 45Internal Revenue Code, Cornell LII, higher for intentional disregard).
Labor hours requirementQualified apprentices must work a share of total labor hours: 15 percent for facilities whose construction began after December 31, 2023 (IRC 45(b)(8)(A))IRC 45Internal Revenue Code, Cornell LII.
Participation requirementEach contractor or subcontractor that “employs 4 or more individuals to perform construction, alteration, or repair work with respect to the construction of a qualified facility shall employ 1 or more qualified apprentices” (IRC 45(b)(8)(C))IRC 45Internal Revenue Code, Cornell LII.
Form 7220The IRS form used “to provide information demonstrating that you have met the prevailing wage and apprenticeship requirements” when claiming the bonus amount.
Elective payAn option that lets tax-exempt and governmental entities receive certain clean energy credits as a payment (IRC 6417)IRC 6417Internal Revenue Code, Cornell LII.

Laws and agencies

TermWhat it means
Copeland ActThe 1934 law that bans kickbacks (18 U.S.C. 874)18 U.S.C. 874United States Code, Cornell LII and requires weekly payroll statements (40 U.S.C. 3145)40 U.S.C. 3145United States Code, Cornell LII. Regulations at 29 CFR part 329 CFR part 3Code of Federal Regulations, eCFR.
CWHSSAThe Contract Work Hours and Safety Standards Act, 40 U.S.C. 370140 U.S.C. 3701United States Code, Cornell LII to 3708: overtime over 40 hours a week on covered federal and federally assisted contracts over $100,000.
Service Contract Act (SCA)The separate law for federal service contracts (41 U.S.C. 6701 and following)41 U.S.C. 6701United States Code, Cornell LII. Construction is excluded from it because the DBA covers construction.
Little Davis-Bacon lawA common name for a state prevailing wage law.
Immigration prevailing wageThe wage floor for H-1B, PERM and other visa programs, set under a different law by DOL's Office of Foreign Labor Certification. See H-1B and PERM prevailing wage.

Questions filers ask

What is the difference between a general and a project wage determination?

A general WD is published on SAM.gov for an area and construction type and has no expiration date. A project WD is issued for one project when no general WD fits and lasts 180 days unless used.

Is a helper the same as an apprentice?

No. An apprentice must be registered in an approved program. A helper is a separate class that appears on a WD only where helpers are an established practice in the area.

Are truck drivers covered?

Only for covered transportation, such as hauling within the site. The 2023 provision that covered drivers' onsite loading and unloading time was vacated by the court on June 24, 2026. See the laborers and mechanics page.

Does the WH-347 have to be used?

No. DOL says the form itself is optional, but covered contractors must still submit the same weekly payroll information and the signed statement.

Are the IRS terms the same as the Davis-Bacon terms?

Mostly. The IRS rules borrow the DOL definitions of laborer and mechanic, construction, wages and site of the work, but add their own terms such as qualified facility and the labor hours requirement.