Clean energy credits: IRS wage and apprentice rules

Section 45Q carbon capture: wage and apprentice rules

Section 45Q pays a credit per metric ton of carbon oxide captured and stored or used. Meeting the prevailing wage and apprenticeship rules multiplies it by five: $17 per ton becomes $85 ($36 becomes $180 for direct air capture) for equipment placed in service after July 4, 2025. Construction must begin before January 1, 2033, and prevailing wages apply to repairs for 12 years. This is general information, not tax advice.

Updated November 21, 2026Sources IRC 45Q (as amended by P.L. 119-21, sec. 70522); IRC 45(b)(7) and (8); Treas. Reg. 1.45-7, 1.45-8 and 1.45-12; Instructions for Forms 8933 and 7220 (12/2025)

What the credit is

Section 45Q, the credit for carbon oxide sequestration, pays an amount for each metric ton of qualified carbon oxide that a taxpayer captures with carbon capture equipment at a qualified facility and then stores in secure geological storage, uses as a tertiary injectant in enhanced oil or gas recovery, or utilizes in a qualifying way. For equipment placed in service after February 9, 2018, the credit runs for 12 years: the carbon oxide must be captured “during the 12-year period beginning on the date the equipment was originally placed in service”. A qualified facility is an industrial facility or direct air capture facility that meets minimum capture amounts, for example at least 1,000 metric tons a year for direct air capture and 12,500 for most other facilities (18,750 for an electricity generating facility, which must also meet a capture design capacity test). The credit carries the prevailing wage and apprenticeship (PWA) rules for the 5x amount.

Base amount vs increased amount

The 2025 law made the base amount the same for every use. The Form 8933 instructions explain that P.L. 119-21 “standardized the base credit amount at $17 per metric ton”, and that “For facilities or equipment placed in service after July 4, 2025, and before 2027, the credit is $17 per metric ton of qualified carbon oxide”. Direct air capture uses $36 in place of $17. From 2027 the amounts are adjusted for inflation. Before this change, utilization and enhanced oil recovery earned a lower base ($12, or $26 for direct air capture) than geologic storage.

The increase is a simple multiplier. Under 45Q(h)(1), for a facility or equipment that meets the PWA requirements, the credit “shall be equal to such amount (determined without regard to this sentence) multiplied by 5”.

Capture type (placed in service after July 4, 2025)Base per metric tonWith PWA (x5, our arithmetic)
Industrial or power facility: storage, EOR or utilization$17$85
Direct air capture: storage, EOR or utilization$36$180

45Q has no 1 MW exception. The only way to get the 5x amount without PWA is the construction-start exception described next.

When the PWA rules are required

45Q(h)(2) sets three cases, all keyed to January 29, 2023 (the date 60 days after Notice 2022-61 was published). The Form 8933 instructions put them in plain terms: the amounts “are multiplied by 5 if any one of the following requirements are met”:

CaseWhat qualifies for 5x
Facility and its carbon capture equipment both began construction before January 29, 20235x without PWA (45Q(h)(2)(C))
New facility (construction began on or after January 29, 2023)5x only if the facility and its equipment meet PWA (45Q(h)(2)(A))
New carbon capture equipment (began on or after January 29, 2023) added to an older facility5x only if the new equipment meets PWA (45Q(h)(2)(B))

The fourth case matters for retrofits. An older industrial plant does not have to go back and prove PWA for work done years ago, but the crews that build and install the new capture equipment are covered, and so are the crews who later alter or repair it.

2026 status after P.L. 119-21

45Q is open to new projects. A qualified facility is one “the construction of which begins before January 1, 2033”, and either the carbon capture equipment begins construction before that date or the original planning and design includes it. That deadline was not changed by the 2025 law. Section 70522 of P.L. 119-21 made two changes:

  1. Parity: the same base amount for storage, enhanced oil or gas recovery and utilization, for facilities or equipment placed in service after July 4, 2025.
  2. Prohibited foreign entities: under new 45Q(f)(10), no credit is allowed for tax years beginning after July 4, 2025 if the taxpayer is a specified foreign entity or a foreign-influenced entity.

Nothing in the 2025 law changed the 45Q PWA paragraph. A 45Q project that begins construction in 2026 needs PWA for the 5x amount, exactly as before. See which credits carry the wage rules in 2026 for the other credits.

Which PWA rules apply

45Q(h)(3) is a full prevailing wage rule. It covers laborers and mechanics employed by the taxpayer or any contractor or subcontractor in “the construction of such facility or equipment”, and, in any tax year within the 12-year credit period, the alteration or repair of the facility or equipment. The Form 7220 instructions confirm the length: “the prevailing wage requirement period for alterations and repairs of facilities is 12 years after the facility was originally placed in service”. That is the longest wage tail of any PWA credit.

Rule45Q
Prevailing wage, constructionYes, facility and carbon capture equipment
Prevailing wage, alteration or repairEach tax year of the 12-year period, tested in the year the work happens
Apprenticeship (labor hours, ratio, participation)Construction only, through 45(b)(8)
Cure for wage failures45(b)(7)(B): back pay plus interest, $5,000 per worker
1 MW exceptionNone
Construction before January 29, 20235x without PWA (see the table above)

The wage rates come from the Davis-Bacon general wage determination for the county and type of construction. Carbon capture equipment at an industrial site and long CO2 pipelines can raise questions about which construction type and which county applies; see the four construction types and the IRS prevailing wage requirement. For the apprentice share (15% of labor hours for construction beginning after 2023), use the apprentice labor hours calculator.

The 12-year tail affects operations contracts. Each year a capture unit is repaired or altered, the crews doing it must be paid prevailing wages, and a failure in one year costs the 5x amount for that year unless cured. O&M and turnaround contracts for 45Q equipment should carry PWA clauses and payroll reporting for the life of the credit, not just the build. See correction and penalties.

What to file

  1. Claim the credit on Form 8933, Carbon Oxide Sequestration Credit.
  2. If you claim the increased amount, attach the statement the Form 8933 instructions require (name, TIN, facility or equipment, registration number if any, construction start facts) under penalties of perjury.
  3. The instructions add: “If construction began on or after January 29, 2023, you must also file Form 7220”, one for each qualified facility.
  4. Each later year of the 12-year period, file Form 7220 for alteration and repair work, or attach the signed statement that none was done.
  5. Report any PWA penalties on Form 4255, and keep the records Treas. Reg. 1.45-12Treas. Reg. 1.45-12Treasury regulations, eCFR calls for (see PWA records).

The statute is at 26 U.S.C. 45Q; the Form 7220 rules are on the Form 7220 page.

Questions filers ask

Does 45Q require prevailing wages?

Only for the 5x amount. A facility or equipment whose construction began on or after January 29, 2023 gets $85 instead of $17 per ton (for equipment placed in service after July 4, 2025) only if it meets PWA. Without PWA, the base credit still applies.

How long do prevailing wages apply after a 45Q facility starts operating?

For alteration and repair, during the 12-year credit period, tested in each tax year in which the work happens.

We are adding capture equipment to a 1990s plant. Does the whole plant need PWA?

No. Under 45Q(h)(2)(B), new carbon capture equipment that began construction on or after January 29, 2023 must meet PWA for its own construction and later alteration or repair.

Is there a 1 MW style exception for small 45Q projects?

No. The 1 MW exception exists only for 45, 45Y, 48 and 48E.

Did the 2025 law end 45Q?

No. Construction must still begin before January 1, 2033. The law equalized the base amount across uses and added prohibited foreign entity restrictions.