Hawaii requires prevailing wages on every contract over $2,000 for construction of a public work that the State, a county or another governmental contracting agency is party to. The Director of the Department of Labor and Industrial Relations (DLIR) sets the rates in a wage rate schedule that contractors must follow as it rises during the job, and a certified copy of all payrolls goes to the contracting agency every week.

Updated November 21, 2026Sources HRS chapter 104 (104-1 to 104-34) and HRS 103-55.6; Hawaii DLIR Wage Standards Division and Research and Statistics pages

At a glance

Hawaii's law is one of the broadest in the country. The threshold is $2,000, "public work" reaches any project paid for to any extent with State or county money or tax-exempt bonds, rates rise during the contract, and overtime is owed by the day and on weekends. DLIR's Wage Standards Division (WSD) enforces it. Its page puts the core rule this way: Hawaii law requires State and county construction projects over $2,000 to pay prevailing wages and “file certified payrolls with the contracting agencies”. We read chapter 104 on the Legislature's site (capitol.hawaii.gov) and the DLIR pages on November 21, 2026.

ItemHawaii ruleWhere it comes from
Who must payContractors and subcontractors on public work for the State, a county or another governmental contracting agencyHRS 104-1, 104-2(a)
ThresholdContract over $2,000 (as of November 2026)HRS 104-2(a)
RatesDLIR modal rate for the State, never below federal rates for the same classHRS 104-2(b)
Rate changesWages rise during the contract when DLIR's schedule risesHRS 104-2(b)(3)
OvertimeSaturdays, Sundays, State holidays and over 8 hours a dayHRS 104-2(c)
Certified payrollWeekly, to the contracting agency, with a fringe benefit reporting formHRS 104-3(a)
RecordsKept during the work and for 3 years afterHRS 104-3(b)
Suspension3 years from new public work on a third violation in the time limitsHRS 104-24(c), 104-25

Which projects are covered

The coverage rule in HRS 104-2(a) is: “This chapter shall apply to every contract in excess of $2,000 for construction of a public work project to which a governmental contracting agency is a party”. "Construction" includes alteration, repair, painting and decorating (104-1). A "contract" includes any agreement, purchase order or voucher over $2,000 for construction of a public work.

The definition of public work is what makes Hawaii broad. It covers any project, including housing developed under HRS 46-15 or chapter 201H, “where the funds or resources required or used to undertake the project are to any extent derived, either directly or indirectly, from public revenues of the State or any county”, or from the sale of bonds whose interest is exempt from state or federal tax (104-1). For 104-2(a), a governmental contracting agency includes any person or entity that causes the building of a public work, directly or indirectly, and any public-private partnership.

RuleWhat it coversSection
Leased buildingsA private construction contract is public work if more than 50% of the assignable square feet is leased or assigned to the State or a county, and the lease came first or the work follows government specifications104-2.5
Nonprofit housing exceptionHousing under 46-15 or chapter 201H is excluded if the project costs less than $500,000 and the bidder or developer is a private nonprofit corporation104-2(a)
No waiverNo provision of the chapter can be set aside by private contract104-2.7
Unadvertised contractsCost-plus contracts and contracts let without advertising are still covered104-30

Covered workers are every laborer and mechanic performing work on the job site (104-2(b)). DLIR issues memos on close calls, including truck drivers on asphalt paving projects (WSD 2026-01, May 21, 2026), sewer line pipe cleaning, floor layers, and owners or partners who appear on certified payrolls.

Rates

The Director sets prevailing wages as the basic hourly rate plus the employer's fringe benefit cost, with separate findings for each. The prevailing rate is “the rate of wages paid to the greatest number of those employed in the State, the modal rate”, in the same class on similar projects (104-2(b)(1)). Hawaii also puts a federal floor under its rates (see the Davis-Bacon section below).

DLIR's Research and Statistics Office publishes the Wage Rate Schedule. As of November 2026 the current schedule is Bulletin 511 (September 14, 2026), with addenda Bulletin 512 (September 15, 2026) and Bulletin 513 (October 2, 2026). “The wage rate schedules are issued on or about the 15th of February and September of each year.”

The rates you bid are not frozen. The statute says rates are adjusted during the contract whatever the original contract says (104-2(b)(3)), and DLIR's page spells out what that means for you: “Whenever the Director determines that the prevailing wage has increased as shown in the wage rate schedule, the contractor must increase the wages accordingly during the performance of the contract.” The schedule already builds in known future increases. Price the job with that in mind.

Pay ruleWhat the law requiresSection
OvertimeOvertime pay for all hours on Saturday, Sunday or a State holiday, and over 8 hours on any other day: at least 1.5 times the basic hourly rate plus fringe benefits, or the union agreement's rates where the rate comes from an agreement104-1, 104-2(c)
Weekly payPay unconditionally at least once a week, wages accrued no more than five working days before payday104-2(d)
PostingPost the rates at the job site and give each worker a copy when hired (not needed where a union agreement applies)104-2(d)
WithholdingThe agency may withhold enough of your payments to cover any underpayment104-2(e)

Parties to a collective bargaining agreement for classes in the rate schedule must send it to the Director within five days after signing (104-34).

Certified payroll

This is the point the DLIR page alone left open, and the statute settles it: payroll is weekly. Every covered contract must provide that a certified copy of all payrolls and a certified copy of a fringe benefit reporting form “shall be submitted weekly to the governmental contracting agency for review” (104-3(a)). The fringe benefit form itemizes health and welfare, pension and annuity, vacation, continuing education and training, and other fringe costs.

The prime contractor carries the subs' paperwork: “The general contractor shall be responsible for the submission of certified copies of the payrolls of all subcontractors.” The certification affirms that the payrolls are correct and complete, that the rates are not less than those in the Director's wage determination attached to the contract, and that each worker's classification matches the work done.

  1. Each week, send the certified payroll and the fringe benefit reporting form (DLIR's or any certified form with the same information) to the governmental contracting agency.
  2. As general contractor, collect and submit certified copies of every subcontractor's payroll.
  3. Keep records for all laborers and mechanics at the site during the work and for three years after: name, classification, rate, the fringe form, daily and weekly hours, deductions and wages paid.
  4. Produce records within ten days of a written request from the agency or DLIR.

DLIR's WSD page links its memo WSD 2017-01 (July 10, 2017) on certified payroll requirements and an optional Department of Accounting and General Services form, the "Statement of Compliance and DAGS-ECP for Payroll Affidavits." Two special cases change the recipient. On a leased building project under 104-2.5 the project owner submits weekly certified payrolls to the leasing agency, and on a project not directly caused by a governmental contracting agency DLIR collects the certified payrolls itself (104-2(g)). For other states, see certified payroll by state.

Registration, fees and training

We found no prevailing wage registration, filing fee or safety training rule in chapter 104 or on the DLIR pages we read (as of November 2026). Contractor licensing matters in another way: for penalties, the "person" named on a violation notice includes the principal responsible managing employee who holds the firm's contractor license (104-24(f)), and both the person and the firm are listed. Check DLIR's Chapter 104 suspension list before you hire a subcontractor.

Apprentices

DLIR publishes an Apprentice Schedule (Apprentice Schedule 511, September 14, 2026) next to the wage rate schedule. Under Hawaii Administrative Rules 12-22-6, as DLIR's page explains, those apprentice rates apply only to contractors in a bona fide apprenticeship program registered with DLIR, and to apprentices whose agreements are registered with or recognized by DLIR and who are individually registered by name.

Hawaii also rewards registered apprenticeship at bid time. On a public works contract with an estimated value of $250,000 or more, the governmental body must cut the bidder's bid amount by five percent for comparison if the bidder is party to a registered apprenticeship agreement for each apprenticeable trade it will use (HRS 103-55.6(a)). The award is still at the bid price. A winning bidder must certify monthly that it stays in a registered program, and losing that status can stop the work or lead to debarment proceedings (103-55.6(c)). For the federal rules, see Davis-Bacon apprentices.

Penalties, debarment and worker claims

DLIR may enter the job site, examine or subpoena records and interview employees during working hours (104-22(a)). Delay costs money fast. If you interfere with or delay an investigation, which includes not providing records, not allowing interviews and falsifying records, the agency withholds all further payments, and “The department shall assess a penalty of $10,000 per project for interference or delay.” Each later day of non-cooperation adds $1,000 per project (104-22(b)).

ViolationPenaltySection
First violation25% of back wages, or $250 per offense up to $2,500, whichever is greater104-24(a)
Second, within 2 years of the first notice100% of back wages, or $500 per offense up to $5,000, whichever is greater104-24(b)
Third, within 3 years of the second noticeTwice the back wages, or $1,000 per offense up to $10,000, whichever is greater, plus suspension from new public work for 3 years104-24(c)
Unpaid wages or penalties (first or second violation)Immediate suspension from all public work until paid in full104-25(a)(1)
Falsified records or delaying an investigationImmediate suspension for 3 years104-25(a)(3)

Each project counts as a separate violation, and for wage and overtime citations each employee on each project is a separate offense (104-24(d), (f)). On a third violation the firm is “Suspended from doing any new work on any public work of a governmental contracting agency for a period of three years”, and no contract may go to a suspended person or to any firm in which it has an interest until the period ends; a contract awarded in violation is void (104-25(c)). DLIR's suspension list, as of April 20, 2026, shows firms suspended for falsified records, delayed investigations and unpaid back wages and penalties.

You can appeal a notice of violation within 20 days; otherwise it becomes final (104-23(b)). Workers have their own remedies. If withheld payments do not cover what is owed, the contractor and its sureties are liable for the unpaid wages “and in an additional equal amount as liquidated damages” (104-27). Workers can sue for themselves and others similarly situated, a joint labor-management committee can seek an injunction, and the court must award attorney's fees and costs. It is no defense that workers agreed to take less (104-28). The agency may also terminate your right to proceed and finish the work at your and your sureties' cost (104-4).

Recent changes

DateChangeSource
October 2, 2026Wage Rate Schedule Bulletin 513 (addendum) issuedDLIR wage rate schedule page
September 14, 2026Wage Rate Schedule Bulletin 511 and Apprentice Schedule 511 issuedDLIR wage rate schedule page
May 21, 2026WSD 2026-01 on chapter 104 and truck drivers on asphalt paving projectsDLIR WSD page
April 20, 2026Latest posted Chapter 104 suspension listDLIR suspension list

The statute itself was last amended in the penalty sections by L 2023, c 51 (sections 104-24 and 104-25), according to the history notes on capitol.hawaii.gov. Watch one future date: parts of 104-2 carry notes that subsections (b)(2) and (g) will be repealed and reenacted, and subsection (i) repealed, on June 30, 2030 (L 2018, c 39). See the state law changes log.

State law and Davis-Bacon on the same job

Hawaii writes the federal rates into its own floor. Except for the special project rates in 104-2(h) and (i), Hawaii prevailing wages “shall be not less than the wages payable under federal law to corresponding classes of laborers and mechanics employed on public works projects in the State” on federal contracts (104-2(b)(2)). Under that rule, a Hawaii rate should not be lower than the federal rate for the same class. Chapter 104 also does not override any minimum wage or maximum hours law (104-31). The saved sources do not say which payroll form to use when a job is covered by both laws, so ask the contracting agency. Start with Davis-Bacon coverage and which prevailing wage rules apply.

Questions filers ask

What is the Hawaii prevailing wage threshold?

Chapter 104 applies to every contract over $2,000 for construction of a public work that a governmental contracting agency is party to (as of November 2026).

How often is certified payroll due in Hawaii?

Weekly. HRS 104-3(a) requires a certified copy of all payrolls and a certified fringe benefit reporting form to be submitted weekly to the governmental contracting agency.

Who submits the subcontractors' payrolls in Hawaii?

The general contractor. The statute makes the general contractor responsible for submitting certified copies of all subcontractors' payrolls.

Do I have to raise wages during a Hawaii contract?

Yes. When DLIR's wage rate schedule shows an increase, you must raise wages during the contract, whatever the original contract says.

Is overtime in Hawaii only over 40 hours?

No. On public work, overtime is owed for all hours on Saturdays, Sundays and State holidays and for hours over 8 on any other day.

What gets a Hawaii contractor suspended?

A third violation within the time limits, failing to pay wages or penalties found due, falsifying records or delaying an investigation. Suspensions run three years or until amounts are paid.