State law
Law
Prevailing wage law in force
Threshold
$2,500 (one trade); $25,000 (more than one trade)
Agency
Minnesota DLI
Certified payroll
Within 14 days of pay period end, to the contracting agency
State prevailing wage laws

Minnesota prevailing wage law

Minnesota requires prevailing wages on construction financed in whole or part by state funds, with very low thresholds: $2,500 for one-trade work and $25,000 when more than one trade is needed. Minnesota DLI sets the rates from an annual contractor survey, and since June 7, 2024 the U.S. Department of Labor has used Minnesota's rates as Davis-Bacon rates for most project types. Businesses that receive large state grants, loans or housing tax credits must certify that they will pay the rates too.

Updated November 21, 2026Sources Minn. Stat. 177.41 to 177.44, 116J.871 and 16C.285; Minnesota DLI prevailing wage pages and FAQs

At a glance

The Minnesota Prevailing Wage Act is Minn. Stat. 177.41 to 177.44, with rules at Minn. R. 5200.1000 to 5200.1120. The Minnesota Department of Labor and Industry (DLI) sets the rates and enforces the law on most projects. State highway contracts under section 177.44 are policed by the Minnesota Department of Transportation (MnDOT). This page uses the statutes as posted by the Revisor and DLI's pages, read November 21, 2026.

ItemMinnesota ruleWhere it comes from
CoveredProjects financed in whole or part by state fundsMinn. Stat. 177.42, subd. 2
ThresholdsNot covered under $2,500 (one trade) or $25,000 (more than one trade)Minn. Stat. 177.43, subd. 7
Business assistanceGrants of $200,000+, loans of $500,000+, sales tax breaks for an area smaller than the state, LIHTC multifamily over 10 unitsMinn. Stat. 116J.871
RatesDLI annual voluntary survey, by county and construction typeDLI survey page
Overtime1.5 times the basic rate past prevailing hours (no more than 8 a day, 40 a week)Minn. Stat. 177.42, 177.43
Certified payrollTo the contracting agency within 14 days after each pay periodMinn. Stat. 177.43, subd. 3

Which projects are covered

A "project" is demolition, erection, construction, alteration, improvement, restoration, remodeling or repair of a public building, structure, facility, land or other public work “financed in whole or part by state funds”. Since the 2023 and 2024 amendments, it also includes such work when the acquisition of property, predesign, design or demolition is state funded. DLI's examples include highways, roads, wastewater plants, public utilities, colleges, schools and park improvements.

The thresholds are among the lowest anywhere. Section 177.43 does not apply when “the estimated total cost of completing the project is less than $2,500 and only one trade or occupation is required to complete it”, or when the cost is under $25,000 and more than one trade is needed (as of November 2026). DLI's state grant page puts the general rule as projects estimated to cost more than $25,000.

State grants, loans and housing credits (116J.871)

Private businesses can be covered too. A state agency may give "financial assistance" only if the recipient certifies to DLI that laborers and mechanics at the project site will be paid the prevailing wage. Financial assistance means:

TypeCovered when
Grant for economic developmentA single business receives $200,000 or more
Loan, loan guaranty or purchaseA single business receives $500,000 or more
Sales tax reduction, credit or abatementApplies to an area smaller than the whole state, for economic development
Low-income housing tax creditsAllocated “for which tax credits are used for multifamily housing projects consisting of more than ten units”

Housing rehabilitation, new housing with less than $100,000 of assistance at one site, and assistance for no more than ten fully detached single-family affordable homes are excluded. DLI's FAQs say homes that share a garage wall are not "fully detached," and one application covering more than ten homes loses the exemption even if they are built in phases. Broadband grants for last-mile infrastructure are exempt by statute; middle-mile projects above the grant or loan amounts are covered.

Work that is not covered

The law does not reach workers who process or manufacture materials, or deliveries by commercial suppliers with a fixed place of business. Aggregate haulers are the exception: the law “applies to laborers or mechanics who deliver mineral aggregate such as sand, gravel, or stone which is incorporated into the work under the contract by depositing the material substantially in place”. Volunteers who work without pay for a nonprofit or political subdivision need not be paid the rate, and the Conservation Corps program is exempt. Landscape maintenance alone is generally not covered, but landscaping done as part of covered work is.

Rates

DLI “conducts an annual voluntary survey of contractors in construction to determine state prevailing-wage rates for commercial, highway/heavy and residential construction and public works projects in Minnesota”. It certifies rates by county. Commercial rates apply to state-funded buildings, including state buildings, colleges and schools; highway/heavy rates apply to highways, roads, airport runways, bridges, power plants, dams and utilities. The survey portal is open year-round, and DLI lists the 2027 notification period as tentatively April 5 to June 4, 2027. DLI also sets minimum truck rental rates for owner-operators.

The prevailing wage rate is the hourly basic rate plus the benefit contributions paid to the largest number of workers in the class, and by statute the rate may not be less than a reasonable and living wage. Rates must be set before bids are requested, written into the contract and posted on the project. A person aggrieved by a rate can ask DLI to reconsider and then, within 20 days, request a contested case hearing.

Hours are part of the rate. Prevailing hours may not be more than 8 a day or 40 a week, and work past them is paid at least 1.5 times the hourly basic rate. Minnesota Paid Leave premiums are not fringe benefits: DLI says employer-paid premiums “need not be reported on certified payroll reports and compliance documents and do not count towards fulfilling prevailing wage requirements”.

Certified payroll

The contract itself must require payroll reporting. Section 177.43, subd. 3 says the contracting agency shall demand, and contractors and subcontractors shall furnish, “copies of any or all payrolls not more than 14 days after the end of each pay period”. The payrolls must contain the data required by section 177.30. On grant-funded work, DLI tells grant recipients and project owners to keep these records for at least three years after final payment. For business assistance under 116J.871, the state agency that awarded the money is treated as the contracting authority, and each employer submits its records there.

DLI may also demand payrolls directly. We found no statewide online payroll portal in the sources read (as of November 2026); filing goes to the contracting agency. For deadlines in other states, see certified payroll by state.

Registration and the responsible contractor test

Minnesota has no prevailing wage contractor registration or fee in the sources read (as of November 2026). The gatekeeping happens at bid time under the responsible contractor law, Minn. Stat. 16C.285. It applies to publicly owned or financed projects where the prime contract is estimated over $50,000 and awarded by low bid or best value. Subcontractors and motor carriers must meet it regardless of the size of their subcontract.

  1. Each bidder verifies under oath, signed by an owner or officer, that it meets the minimum criteria. One of them is that the contractor “has a valid federal tax identification number or a valid Social Security number if an individual”.
  2. The contractor must not have violated the prevailing wage act (177.41 to 177.44) or the federal Davis-Bacon Act in the three years before the verification, as the statute defines a violation (for example a final DLI order to comply, or repeated underpayments totaling $25,000 or more).
  3. The prime lists its first-tier subcontractors and, before signing the contract, collects sworn verifications from them.
  4. Subcontractors added later must verify, and the prime files a supplemental verification within 14 days.

A prime is responsible for a first-tier sub's false verification only if it accepted the statement knowing it was false. Still, the federal tax ID item is the easiest one to check yourself: match each sub's legal name and EIN before it starts work. For the federal side of the same idea, see Davis-Bacon withholding and debarment.

Apprentices

Apprentices on state projects are paid under their registered apprenticeship agreement, not the journeyworker rate, but only if they meet DLI's definition: registered in a program approved by the U.S. Department of Labor or a state apprenticeship agency, or in the first 90 days of probation and certified as eligible. Anyone else on the payroll gets the full rate for the classification of work. DLI warns that “The titles of unskilled worker, trainee, laborer, registered or unlicensed trade are not to be used interchangeably with” "apprentice" to avoid the law. See also Davis-Bacon apprentices.

Penalties and enforcement

Underpayment is a crime. Section 177.43, subd. 5 makes it a misdemeanor for a contractor, subcontractor or agent to pay a worker on the site less than the contract rate, or for a state official to sign a covered contract without the required terms. The misdemeanor “is punishable by a fine of not more than $700, or imprisonment for not more than 90 days, or both”, and each day is a separate offense. A business that certified under 116J.871 and then fails to pay also commits a misdemeanor.

Enforcement toolRuleSection
InvestigationsDLI must employ at least three investigators for on-site reviews, complaints and training177.43, subd. 6
Withholding ordersWith a compliance order, DLI orders the contracting authority to hold back enough from the prime to cover back wages177.43, subd. 6a
Final payment noticeDuring an investigation, DLI can require 90 days' notice before final payment177.43, subd. 6a
Agency liabilityA contracting authority that leaves out the wage determination or DLI's contract language must make the contractor whole for higher wages177.43, subd. 3
State highway contractsMisdemeanor, up to $300 or 90 days; inducing a worker to give up wages up to $1,000 or 1 year177.44, subd. 6
Future bidsA violation in the prior 3 years fails the responsible contractor test16C.285, subd. 3

DLI says that when an employer pays less than the prevailing wage, it requires back wages to the worker and can assess penalties. Workers file complaints with DLI's Prevailing Wage unit. The sources read do not set out a separate private lawsuit right under the prevailing wage act, so we leave that out.

Recent changes

DateChangeSource
2023 (c. 53)Project definition amended; it now names work where property acquisition, predesign, design or demolition is state funded; 116J.871 amended177.42 and 116J.871 history
2024 (c. 110)Further amendment to the project definition in 177.42177.42 history
2024 (c. 85, c. 127)116J.871 amended again (c. 127 changed subds. 1, 2 and 4); the current text counts LIHTC multifamily projects over 10 units as financial assistance116J.871 history
June 7, 2024U.S. DOL adopted Minnesota prevailing wage rates as Davis-Bacon rates for most project typesDLI FAQ
Posted, undatedDLI marks as new its guidance on wood frame carpentry and the Low-Income Housing Tax CreditDLI prevailing wage page

DLI says the 2023 and 2024 changes to the definition of "project" clarify it and align it with how DLI has long applied the law, rather than changing it in substance. The LIHTC rule matters most for housing developers: under the current text, a multifamily project of more than ten units that receives housing tax credits carries Minnesota prevailing wage duties for everyone working on site.

State law and Davis-Bacon on the same job

Both laws apply when a project has state and federal money. DLI's FAQ says “A contractor is required to pay the rate that is most beneficial to the employee.” The gap between the two is small in Minnesota because, in DLI's words, “As of June 7, 2024, the U.S. Department of Labor adopted Minnesota prevailing-wage rates as federal Davis-Bacon rates for most types of projects.” The paperwork is still separate: a federally assisted project needs the federal certified payroll (see the WH-347 guide) and the state contract still requires payrolls to the contracting agency within 14 days. Check overtime too, since the state counts daily hours past 8.

Questions filers ask

Does a $20,000 state-funded job with one trade need prevailing wage?

Yes. The one-trade exemption applies only under $2,500. The $25,000 exemption is for projects that need more than one trade.

Do LIHTC housing projects in Minnesota pay prevailing wage?

Yes, when low-income housing tax credits are used for a multifamily project of more than ten units. The developer certifies to DLI that site workers will be paid the rate.

When is certified payroll due in Minnesota?

No more than 14 days after the end of each pay period, to the contracting agency (or, for business assistance, the agency that awarded the money).

Do Paid Leave premiums count toward the fringe?

No. DLI says employer-paid Minnesota Paid Leave premiums do not count toward prevailing wage, and an employee deduction cannot push pay below the rate.

If both Davis-Bacon and Minnesota law apply, which rate do I pay?

The rate most beneficial to the worker. Since June 7, 2024, DOL has used Minnesota's rates as Davis-Bacon rates for most project types, so the two often match.

Who counts as an apprentice?

Only a worker registered in a DOL or state-approved program, or in the first 90 days of probation and certified as eligible. Everyone else gets the full classification rate.

Sources