Clean energy credits: IRS wage and apprentice rules

The IRS prevailing wage requirement for clean energy credits

To claim the increased credit, the owner must make sure every laborer and mechanic on the job, including those of every contractor and subcontractor, is paid at least the Davis-Bacon rates DOL publishes for the area and type of construction. The rule covers construction and, for most credits, alteration or repair for 5 to 12 years after the facility is placed in service. This page is general information, not tax advice.

Updated November 21, 2026Sources IRC 45(b)(7) and parallel sections; Treas. Reg. 1.45-7; IRS PWA FAQ; Form 7220 instructions; DOL IRA page

The rule in one paragraph

Section 45(b)(7)(A) requires the taxpayer to ensure that laborers and mechanics employed by it or any contractor or subcontractor are paid at least the prevailing rates for similar work in the locality “as most recently determined by the Secretary of Labor, in accordance with subchapter IV of chapter 31 of title 40, United States Code”. That is the Davis-Bacon Act. The other credits (45Y, 45Q, 45V, 45Z, 48, 48E, 30C, 45L, 45U, 48C and 179D) use the same words or point back to section 45. The detailed rules are in Treas. Reg. 1.45-7, effective for facilities placed in service in tax years ending after June 25, 2024 and construction beginning after that date. This page is general information, not tax advice.

The owner carries the risk. Treas. Reg. 1.45-7(b)(6)Treas. Reg. 1.45-7Treasury regulations, eCFR says “The taxpayer is solely responsible for ensuring that laborers and mechanics are paid wages not less than the prevailing rate whether employed directly by the taxpayer, a contractor, or a subcontractor”. A sub's mistake is the owner's failure, which is why owners push the wage rules down into every subcontract.

Who must be paid prevailing wages

Laborers and mechanics are people whose duties are manual or physical, including those who use tools or do the work of a trade. Apprentices and helpers are included. People whose duties are mainly administrative, executive or clerical, and exempt professionals under 29 CFR part 54129 CFR part 541Code of Federal Regulations, eCFR (an architect or a design engineer, for example), are not. A working foreperson is covered for the manual hours if they are “Working forepersons who devote more than 20 percent of their time during a workweek to laborer or mechanic duties” and are not exempt under part 541. The regulation's example is a foreperson with 16 hours of electrician work in a 40-hour week: those 16 hours must be paid at the electrician rate.

Employment status does not matter. Employed means doing the work “regardless of whether the individual would be characterized as an employee or an independent contractor for other Federal tax purposes”. The IRS FAQ adds: “Laborers and mechanics who are independent contractors for employment tax purposes may be considered employed for purposes of the IRA prevailing wage requirements.” So a crew paid on a 1099-NEC still needs the rates and still goes on the payroll records. (For the 1099-NEC side of paying subcontractors, see tincompliance.com.)

Indian Tribal governments are excepted for their own employees (Treas. Reg. 1.45-7(a)(3))Treas. Reg. 1.45-7Treasury regulations, eCFR, but not for work done through contractors.

Which rates apply: the general wage determination

Rates come from DOL general wage determinations on SAM.gov for the type of construction (building, heavy, highway or residential) and the county. Under Treas. Reg. 1.45-7(b)(2)Treas. Reg. 1.45-7Treasury regulations, eCFR and (b)(5), the applicable determination is the one in effect when the taxpayer (or its agent) signs the contract with the contractor. “The applicable general wage determination will continue in effect for any additional contracts executed by such contractor with any subcontractors”. In practice:

SituationWhich wage determination
One EPC contractThe WD in effect when the owner and EPC contractor sign; it flows to every sub under that contract
Several prime contractsEach prime contract uses the WD in effect when that contract was signed
No contract (owner self-performs), or date unknownThe WD in effect when the work starts
Contract changed to add substantial work, or an option exercisedA new WD, as of the date the work or option is agreed
Extra time only, or incidental extra workNo new WD needed
Open-ended alteration or repair contract after placed in serviceRates updated every year on the contract anniversary
Work in more than one county or more than one construction typeEach area and type uses its own WD

For the last row, the IRS FAQ notes that a facility can need more than one WD when two construction types, such as heavy and building, apply. For a walk through the WD itself, see how to read a wage determination.

No rate, or a missing classification

If DOL has no general wage determination for the area and type of construction, or the WD lacks a classification you need, the taxpayer, contractor or subcontractor asks DOL's Wage and Hour Division for a supplemental wage determination or an additional classification and rate, at IRAprevailingwage@dol.gov. Supplemental WD requests go no more than 90 days before the contract is expected to be signed. A supplemental WD is good for 180 days unless it is put into the contract, and DOL answers additional classification requests within 30 days or says it needs more time. Rates issued after work started apply back to the start: “If a supplemental wage determination or additional classification and wage rate is issued after construction, alteration, or repair of the facility has started, the applicable prevailing rates apply retroactively to the date construction started.” The 12 items a request needs and the timing are on supplemental wage determinations for clean energy projects. Offshore facilities may use the WD for the nearest onshore area (Treas. Reg. 1.45-7(b)(3)(iv))Treas. Reg. 1.45-7Treasury regulations, eCFR.

What counts as wages

The prevailing wage is the basic hourly rate plus the fringe benefit rate on the WD. Under Treas. Reg. 1.45-7(b)(6)Treas. Reg. 1.45-7Treasury regulations, eCFR, you may pay the whole amount in cash, through bona fide fringe benefit plans, or a mix, and the Davis-Bacon fringe rules in 29 CFR 5.2529 CFR 5.25Code of Federal Regulations, eCFR to 5.33 apply, including annualization. Benefits that another law requires (workers' compensation, unemployment insurance) do not count. The cash and plan math is on the fringe benefits page.

Wages must be paid on the employer's regular payroll schedule, in full, without deductions other than those required by law or allowed by DOL's regulations.

Construction, repair and maintenance

Covered work is construction, alteration or repair as defined for Davis-Bacon in 29 CFR 5.229 CFR 5.2Code of Federal Regulations, eCFR (read with the June 24, 2026 judgment in AGC v. DOL, No. 5:23-cv-272-H (N.D. Tex.), which vacated parts of the 2023 definitions; see laborers and mechanics). Repair fixes something that is not working, corrects a separate defect, or improves strength, safety, capacity or efficiency. Maintenance is not covered: “Construction, alteration, or repair does not include work that is ordinary and regular in nature that is designed to maintain and preserve existing functionalities of a facility after it is placed in service.” The regulation's examples of maintenance are regular inspections, cleaning, replacing filters and light bulbs, and calibrating equipment.

Timing changes the answer. The same task before the facility is placed in service may be construction: “However, such work that occurs before the facility is placed in service may constitute construction for which prevailing wages must be paid in order to claim the increased credit amount.”

After placed in service, sort each work order. A scheduled inverter inspection is maintenance. Replacing a failed transformer or adding storage capacity is repair or alteration. When in doubt, the regulation says it turns on the facts and circumstances, so document why you classed the work as you did.

Where the work happens

The locality is the county (or similar area) where the facility will be placed in service. It also includes secondary sites where a significant portion of the facility, such as a whole module or completed structure, is built for that facility at a site set up or dedicated to it, and adjacent dedicated support sites such as job headquarters, tool yards, batch plants and borrow pits (Treas. Reg. 1.45-7(d)(7))Treas. Reg. 1.45-7Treasury regulations, eCFR. Materials and prefabricated parts delivered to the site are not a significant portion. Work at a secondary site uses the WD for that site's area.

How long the rule lasts, by credit

CreditConstructionAlteration or repair after placed in service
45, 45Y, 45VYesAny year of the 10-year credit period
45QYes12 years after placed in service
48, 48EYes5 years, with recapture of the bonus
45ZYes (facilities placed in service after 2024)Yes; pre-2025 facilities only for work after 2024
45UNoYes (the only test)
30C, 45L, 179D, 48CYesNo

The periods come from the Code and the Form 7220 instructions. For each year in the period, the rule applies only if alteration or repair happens: “If no alteration or repair work occurs during the taxable year(s) with respect to the qualified facility after the facility is placed in service, the taxpayer is deemed to satisfy the Prevailing Wage Requirements with respect to such taxable year.” Form 7220 is still filed for those years, with a statement that no alteration or repair occurred.

Paying apprentices

Registered apprentices may be paid the program's progression rate (a percentage of the journeyworker rate on the WD) and the program's fringe benefits, but only within the program's apprentice to journeyworker ratio. Apprentices over the ratio get the full journeyworker rate. And “Any individual listed on payroll at an apprenticeship wage, who is not participating in a registered apprenticeship program, must be paid not less than the applicable wage rate on the wage determination for the classification of work actually performed”. The labor hour and participation tests are on the apprenticeship requirement page.

How it differs from a Davis-Bacon contract

The rates are Davis-Bacon rates, but the program is the IRS's. DOL's IRA page says that under the Inflation Reduction Act “a taxpayer is not subject to the regulations implementing the Davis-Bacon Act and the Related Acts”, including DOL enforcement. There is no contract clause from an agency, no withholding of contract payments and no DOL debarment for the tax rules. Instead, the cost of a failure is the credit itself, or the correction payments and IRS penalty that save it. If the project also takes a federal grant or loan under a Related Act, both sets of rules apply (see which rules apply). State prevailing wage laws also still apply where they reach the project.

What owners and contractors do in practice

  1. Pick the WD (or WDs) on the day the prime contract is signed, and attach them to the contract and every subcontract.
  2. Put the wage, record and cooperation duties in every subcontract. The IRS lists contract clauses among the facts it weighs for intentional disregard.
  3. Post the rates at the site or give workers written notice, with a way to report underpayment without retaliation.
  4. Collect payroll records from every tier (the WH-347 format works) and review rates and classifications at least quarterly.
  5. Fix underpayments fast. For small failures, paying the worker by the end of the month after the quarter can avoid the $5,000 per worker penalty; see fixing PWA failures and the penalty estimator.
  6. Keep the records the IRS expects and report on Form 7220 with the return.

Questions filers ask

Is the IRA prevailing wage the same as Davis-Bacon?

The rates are the same DOL Davis-Bacon rates, but the rules around them are the IRS's (Treas. Reg. 1.45-7)Treas. Reg. 1.45-7Treasury regulations, eCFR, not DOL's contract regulations. DOL says a taxpayer is not subject to the Davis-Bacon and Related Acts regulations, including DOL enforcement, under the IRA.

Do O&M crews need prevailing wages?

Not for routine, scheduled maintenance after the facility is placed in service. Repair and alteration during the credit's period are covered. The same work before the facility is placed in service may count as construction.

Which wage determination do we use if the EPC contract was signed in 2025 but work starts in 2026?

The one in effect when the owner and EPC contractor signed the contract, unless the contract is later changed to add substantial work or an option is exercised.

Do independent contractors on the site count?

Yes. Anyone doing laborer or mechanic work counts, whether or not they are an employee for other tax purposes.

Do we need certified payroll?

The IRS rules do not require DOL's WH-347 or weekly submission to an agency, but Treas. Reg. 1.45-12Treas. Reg. 1.45-12Treasury regulations, eCFR lists completed WH-347s among the records that may show compliance, and owners usually require weekly payrolls from every tier.

What if a sub underpaid a worker?

The owner can cure by paying the worker the shortfall plus interest and paying the IRS $5,000 per underpaid worker for the year, with a waiver for small, fast fixes. See the correction page.